8942 W ELLIS AVE 90034
Certificate Information: 8942 W ELLIS AVE 90034
- Application / Permit
- 22016-10000-35370
- Plan Check / Job No.
- B22LA23701
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Bakery
- Work Description
- Change of use of existing storage & office warehouse to commercial wholesale bakery, storage, and office
- Permit Issued
- Issued on 7/6/2023
- Issuing Office
- Current Status
- CofO Issued on 1/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/1/2022 | HERNAN ARREOLA |
| Corrections Issued | 12/12/2022 | HERNAN ARREOLA |
| Quality Review Completed | 12/29/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 5/31/2023 | HERNAN ARREOLA |
| Applicant returned to address corrections | 6/30/2023 | HERNAN ARREOLA |
| Plan Check Approved | 7/5/2023 | HERNAN ARREOLA |
| Issued | 7/6/2023 | APPLICANT |
| CofO in Progress | 1/26/2024 | GRANT WOODS |
| Permit Finaled | 1/31/2024 | DAVID TSAU |
| CofO Issued | 1/31/2024 | DAVID TSAU |
| Permit Finaled | 1/31/2024 | DAVID TSAU |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/25/2023 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 1/25/2023 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 4/28/2023 | KYLE WINSTON |
| Food Service Establishment | Cleared | 6/6/2023 | KENNETH BROWNE |
| DAS Clearance | Cleared | 6/26/2023 | HERNAN ARREOLA |
| Food establishment approval | Cleared | 7/5/2023 | LACDHS APPROVED |
Contact Information
| Architect | Corona,, Victor M; Lic. No.: NA25767 | , |
| Contractor | Ocean Construction; Lic. No.: 833486-B | , |
| Contractor | Ocean Spaulding Inc; Lic. No.: 833486-B | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/25/2023 | Partial Approval | FARHAD DADBIN |
| Light Gage Steel Frame | 8/3/2023 | Partial Approval | FARHAD DADBIN |
| Drywall Nailing | 8/9/2023 | Approved | FARHAD DADBIN |
| T-Bar Ceiling | 9/22/2023 | Not Ready for Inspection | FARHAD DADBIN |
| T-Bar Ceiling | 10/25/2023 | Not Ready for Inspection | FARHAD DADBIN |
| T-Bar Ceiling | 11/9/2023 | Conditional Approval | FARHAD DADBIN |
| Final | 12/22/2023 | Not Ready for Inspection | GRANT WOODS |
| Final | 1/26/2024 | Conditional Approval | GRANT WOODS |
| Reinforced Masonry Frame | 1/26/2024 | Approved | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 1/26/2024 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 1/26/2024 | Approved | GRANT WOODS |