239 1/2 S AVENUE 18 90031

Certificate Information: 239 1/2 S AVENUE 18 90031

Application / Permit
22016-10000-35364
Plan Check / Job No.
B22LA23695
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing detached garage into accessory dwelling unit per CA Govt. Code 65852.2(e)(1)(A). All work per WFPP.
Permit Issued
Issued on 10/31/2023
Issuing Office
Metro
Current Status
CofO Issued on 2/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2022 APPLICANT
Assigned to Plan Check Engineer 11/30/2022 KHUONG TRUONG
Corrections Issued 11/30/2022 KHUONG TRUONG
Applicant returned to address corrections 1/3/2023 VICTOR CHEN
Applicant returned to address corrections 4/11/2023 JOSEPH RAFOLS
Applicant returned to address corrections 7/26/2023 WEIJIAN HUANG
Applicant returned to address corrections 8/22/2023 MINA HABILI
No Progress 10/20/2023 DANIEL SMILEY
Plan Check Approved 10/24/2023 VICTOR CHEN
No Progress 10/24/2023 VICTOR CHEN
Plan Check Approved 10/24/2023 VICTOR CHEN
Issued 10/31/2023 APPLICANT
CofO in Progress 2/14/2025 ALIZAH MAYAGOITIA
Permit Finaled 2/14/2025 DEROLD HAUFF
CofO Issued 2/14/2025 DEROLD HAUFF
Permit Finaled 2/14/2025 DEROLD HAUFF

Permit Application Clearance Information

Specific Plan Cleared 2/8/2023 NURI CHO
Address approval Cleared 3/18/2023 CHRISTOPHER ROCHA
Sewer availability Cleared 3/18/2023 CHRISTOPHER ROCHA
Construction within easement Cleared 6/7/2023 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 9/11/2023 AMY LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/11/2023 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 6/10/2024 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 6/10/2024 Corrections Issued OSVALDO PARAMO
Wood Frame 6/10/2024 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 6/24/2024 No Access for Inspection OSVALDO PARAMO
PLUMBING-Rough 7/10/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Special/Order Compliance 7/10/2024 Partial Inspection ARTHUR NEGRETE
ELECTRICAL-Rough 8/6/2024 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 8/6/2024 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Rough 8/14/2024 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 8/14/2024 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Rough 8/23/2024 Approved ALIZAH MAYAGOITIA
HVAC-Rough 8/23/2024 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 8/29/2024 Corrections Issued OSVALDO PARAMO
Special/Order Compliance 8/29/2024 Partial Inspection LUIS CASTRO
PLUMBING-Rough 9/4/2024 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 9/17/2024 Approved OSVALDO PARAMO
Green Building Rough 9/17/2024 Approved OSVALDO PARAMO
MERV13>=Rough 9/17/2024 Approved OSVALDO PARAMO
Sewer 9/18/2024 Approved ALIZAH MAYAGOITIA
Insulation 9/26/2024 Approved LUIS CASTRO
Drywall Nailing 10/8/2024 Order to Comply Issued JOHN QUINTANILLA
Final 11/26/2024 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 11/26/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
MERV13>=Final 11/26/2024 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 11/26/2024 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 11/26/2024 Approved ALIZAH MAYAGOITIA
Final 1/6/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 1/6/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 1/6/2025 SGSOV Approved ALIZAH MAYAGOITIA
Final 2/5/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 2/5/2025 Approved ALIZAH MAYAGOITIA
Final 2/11/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 2/13/2025 Partial Approval ALIZAH MAYAGOITIA
Final 2/14/2025 OK to Issue CofO ALIZAH MAYAGOITIA