239 1/2 S AVENUE 18 90031
Certificate Information: 239 1/2 S AVENUE 18 90031
- Application / Permit
- 22016-10000-35364
- Plan Check / Job No.
- B22LA23695
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing detached garage into accessory dwelling unit per CA Govt. Code 65852.2(e)(1)(A). All work per WFPP.
- Permit Issued
- Issued on 10/31/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2022 | KHUONG TRUONG |
| Corrections Issued | 11/30/2022 | KHUONG TRUONG |
| Applicant returned to address corrections | 1/3/2023 | VICTOR CHEN |
| Applicant returned to address corrections | 4/11/2023 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 7/26/2023 | WEIJIAN HUANG |
| Applicant returned to address corrections | 8/22/2023 | MINA HABILI |
| No Progress | 10/20/2023 | DANIEL SMILEY |
| Plan Check Approved | 10/24/2023 | VICTOR CHEN |
| No Progress | 10/24/2023 | VICTOR CHEN |
| Plan Check Approved | 10/24/2023 | VICTOR CHEN |
| Issued | 10/31/2023 | APPLICANT |
| CofO in Progress | 2/14/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 2/14/2025 | DEROLD HAUFF |
| CofO Issued | 2/14/2025 | DEROLD HAUFF |
| Permit Finaled | 2/14/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Specific Plan | Cleared | 2/8/2023 | NURI CHO |
| Address approval | Cleared | 3/18/2023 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 3/18/2023 | CHRISTOPHER ROCHA |
| Construction within easement | Cleared | 6/7/2023 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2023 | AMY LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/11/2023 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 6/10/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 6/10/2024 | Corrections Issued | OSVALDO PARAMO |
| Wood Frame | 6/10/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 6/24/2024 | No Access for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 7/10/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Special/Order Compliance | 7/10/2024 | Partial Inspection | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 8/6/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 8/6/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 8/14/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 8/14/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 8/23/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 8/23/2024 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 8/29/2024 | Corrections Issued | OSVALDO PARAMO |
| Special/Order Compliance | 8/29/2024 | Partial Inspection | LUIS CASTRO |
| PLUMBING-Rough | 9/4/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 9/17/2024 | Approved | OSVALDO PARAMO |
| Green Building Rough | 9/17/2024 | Approved | OSVALDO PARAMO |
| MERV13>=Rough | 9/17/2024 | Approved | OSVALDO PARAMO |
| Sewer | 9/18/2024 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 9/26/2024 | Approved | LUIS CASTRO |
| Drywall Nailing | 10/8/2024 | Order to Comply Issued | JOHN QUINTANILLA |
| Final | 11/26/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 11/26/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| MERV13>=Final | 11/26/2024 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 11/26/2024 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 11/26/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 1/6/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 1/6/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 1/6/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Final | 2/5/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 2/5/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 2/11/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 2/13/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Final | 2/14/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |