213 W 118TH ST 90061

Certificate Information: 213 W 118TH ST 90061

Application / Permit
22016-10000-35352
Plan Check / Job No.
B22LA23680
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO MASTER BEDROOM WITH FULL BATHROOM PER WFPP "COMPLY WITH DEPARTMENT ERROR EFFECTIVE DATE 11/21/22. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE."
Permit Issued
Issued on 5/22/2023
Issuing Office
Metro
Current Status
CofO Issued on 10/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2022 APPLICANT
Assigned to Plan Check Engineer 11/28/2022 LAWRENCE QUIRANTE
Corrections Issued 12/1/2022 LAWRENCE QUIRANTE
Building Plans Picked Up 12/6/2022 APPLICANT
Applicant returned to address corrections 2/22/2023 VICTOR CHEN
Applicant returned to address corrections 5/1/2023 CRISTINA SALAZAR
Plan Check Approved 5/22/2023 MINA HABILI
Issued 5/22/2023 APPLICANT
CofO in Progress 10/17/2023 BRIAN CHRISTIAN
Permit Finaled 10/24/2023 BRUCE TODD
CofO Issued 10/24/2023 BRUCE TODD
Permit Finaled 10/24/2023 BRUCE TODD

Permit Application Clearance Information

Address approval Cleared 1/5/2023 WALLIE JONG
Sewer availability Cleared 1/5/2023 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 5/22/2023 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/13/2023 Approved BRIAN CHRISTIAN
BUILDING-Rough-Frame 8/10/2023 Approved BRIAN CHRISTIAN
Drywall Nailing 8/10/2023 Approved BRIAN CHRISTIAN
ELECTRICAL-Rough 8/10/2023 Corrections Issued BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 8/10/2023 Approved BRIAN CHRISTIAN
Green Building Rough 8/10/2023 Approved BRIAN CHRISTIAN
Insulation 8/10/2023 Approved BRIAN CHRISTIAN
ELECTRICAL-Final 9/7/2023 Approved BRIAN CHRISTIAN
Green Building Final 9/7/2023 Approved BRIAN CHRISTIAN
PLUMBING-Final 9/7/2023 Approved BRIAN CHRISTIAN
SGSOV-Seismic Gas S/O Valve 9/7/2023 SGSOV Approved BRIAN CHRISTIAN
Smoke Detectors 9/7/2023 Approved BRIAN CHRISTIAN
Final 10/17/2023 OK to Issue CofO BRIAN CHRISTIAN
HVAC-Final 10/17/2023 Approved BRIAN CHRISTIAN