213 W 118TH ST 90061
Certificate Information: 213 W 118TH ST 90061
- Application / Permit
- 22016-10000-35352
- Plan Check / Job No.
- B22LA23680
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO MASTER BEDROOM WITH FULL BATHROOM PER WFPP "COMPLY WITH DEPARTMENT ERROR EFFECTIVE DATE 11/21/22. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE."
- Permit Issued
- Issued on 5/22/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/28/2022 | LAWRENCE QUIRANTE |
| Corrections Issued | 12/1/2022 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 12/6/2022 | APPLICANT |
| Applicant returned to address corrections | 2/22/2023 | VICTOR CHEN |
| Applicant returned to address corrections | 5/1/2023 | CRISTINA SALAZAR |
| Plan Check Approved | 5/22/2023 | MINA HABILI |
| Issued | 5/22/2023 | APPLICANT |
| CofO in Progress | 10/17/2023 | BRIAN CHRISTIAN |
| Permit Finaled | 10/24/2023 | BRUCE TODD |
| CofO Issued | 10/24/2023 | BRUCE TODD |
| Permit Finaled | 10/24/2023 | BRUCE TODD |
Permit Application Clearance Information
| Address approval | Cleared | 1/5/2023 | WALLIE JONG |
| Sewer availability | Cleared | 1/5/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 5/22/2023 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KELLY WARNER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL BECKER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| KEITH EDGHILL, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GONZALEZ, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/13/2023 | Approved | BRIAN CHRISTIAN |
| BUILDING-Rough-Frame | 8/10/2023 | Approved | BRIAN CHRISTIAN |
| Drywall Nailing | 8/10/2023 | Approved | BRIAN CHRISTIAN |
| ELECTRICAL-Rough | 8/10/2023 | Corrections Issued | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Approved | BRIAN CHRISTIAN |
| Green Building Rough | 8/10/2023 | Approved | BRIAN CHRISTIAN |
| Insulation | 8/10/2023 | Approved | BRIAN CHRISTIAN |
| ELECTRICAL-Final | 9/7/2023 | Approved | BRIAN CHRISTIAN |
| Green Building Final | 9/7/2023 | Approved | BRIAN CHRISTIAN |
| PLUMBING-Final | 9/7/2023 | Approved | BRIAN CHRISTIAN |
| SGSOV-Seismic Gas S/O Valve | 9/7/2023 | SGSOV Approved | BRIAN CHRISTIAN |
| Smoke Detectors | 9/7/2023 | Approved | BRIAN CHRISTIAN |
| Final | 10/17/2023 | OK to Issue CofO | BRIAN CHRISTIAN |
| HVAC-Final | 10/17/2023 | Approved | BRIAN CHRISTIAN |