2221 N BOWMONT DR 90210
Certificate Information: 2221 N BOWMONT DR 90210
- Application / Permit
- 22016-10000-35318
- Plan Check / Job No.
- B22LA23658
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *eplan* Exterior and interior remodel to (E) SFD. COMPLY WITH DEPARTMENT ORDER effective date 08/22/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 1/16/2023
- Issuing Office
- Current Status
- Permit Finaled on 1/29/2024
Permit Application Status History
| Submitted | 11/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/28/2022 | JASON JANGADA |
| Corrections Issued | 11/29/2022 | JASON JANGADA |
| Plan Check Approved | 1/4/2023 | FARSHAD ALIMOHAMADI |
| Issued | 1/16/2023 | APPLICANT |
| Permit Finaled | 1/26/2024 | PETER RUBIO |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/1/2022 | KIRK LINKLATER |
| Specific Plan | Cleared | 12/29/2022 | OLGA AYALA |
Contact Information
| Architect | Suzuki,, Yasuhito; Lic. No.: NA26793 | , |
| Contractor | Cal - For Construction Inc; Lic. No.: 1021371-B | , |
| Engineer | Mina,, Joseph; Lic. No.: NA53465 | , |
Inspector Information
| PETER RUBIO, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN TCHANG, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN TAGUINES, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 2/28/2023 | Not Ready for Inspection | ROBERT CHAVEZ |
| ELECTRICAL-Rough | 2/28/2023 | Not Ready for Inspection | ROBERT CHAVEZ |
| Footing/Foundation/Slab | 2/28/2023 | Corrections Issued | ROBERT CHAVEZ |
| PLUMBING-Rough | 2/28/2023 | Not Ready for Inspection | ROBERT CHAVEZ |
| BUILDING-Rough-Frame | 3/16/2023 | Not Ready for Inspection | ROBERT CHAVEZ |
| Footing/Foundation/Slab | 3/16/2023 | Approved | ROBERT CHAVEZ |
| BUILDING-Rough-Frame | 4/28/2023 | Approved | ROBERT CHAVEZ |
| ELECTRICAL-Rough | 4/28/2023 | Approved | ROBERT CHAVEZ |
| Interior/Exterior Lathing | 4/28/2023 | Approved | ROBERT CHAVEZ |
| PLUMBING-Rough | 4/28/2023 | Approved | ROBERT CHAVEZ |
| Shower Pan | 4/28/2023 | Approved | ROBERT CHAVEZ |
| Insulation | 6/6/2023 | Approved | PETER RUBIO |
| Drywall Nailing | 6/13/2023 | Approved | PETER RUBIO |
| Final | 11/21/2023 | Partial Approval | PETER RUBIO |
| SGSOV-Seismic Gas S/O Valve | 11/21/2023 | SGSOV Approved | PETER RUBIO |
| Smoke Detectors | 11/21/2023 | Approved | PETER RUBIO |
| Final | 1/26/2024 | Permit Finaled | PETER RUBIO |