1980 N LAUREL CANYON ROAD 90046
Certificate Information: 1980 N LAUREL CANYON ROAD 90046
- Application / Permit
- 22016-10000-35301
- Plan Check / Job No.
- B22LA23644
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR AND EXTERIOR REMODEL ONLY: REPAIR THE EXISTING CONCRETE DECK, REPLACE THE FRONT EXTERIOR BENT WALL LOCATED ON THE NORTHWEST SIDE OF THE HOUSE (LIVING ROOM), AND REPLACE THE ROOF RAFTERS AND ROOFING LOCATED IN THE LIVING ROOM . REMODEL EXISTING KITCHEN AND BATHROOM WITH (N) NO-BEARING PARTITION WALLS. RAISE EXISTING ROOF ON THE RESTROOM AT THE SECOND FLOOR.
- Permit Issued
- Issued on 3/20/2023
- Issuing Office
- Current Status
- Permit Finaled on 3/7/2025
Permit Application Status History
| Submitted | 11/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2022 | SUNMIN LEE |
| Corrections Issued | 12/1/2022 | SUNMIN LEE |
| Applicant returned to address corrections | 2/23/2023 | SELLA BENYAMIN |
| Applicant returned to address corrections | 3/6/2023 | SELLA BENYAMIN |
| Plan Check Approved | 3/12/2023 | JOE VO |
| Issued | 3/20/2023 | APPLICANT |
| Permit Finaled | 3/6/2025 | ROY SPAULDING |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 12/12/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 12/12/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2022 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 1/18/2023 | MANUEL TEJADA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/14/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 8/15/2023 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 8/15/2023 | Corrections Issued | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 8/30/2023 | Approved | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 8/30/2023 | Approved | RAUL BARAJAS |
| Footing/Foundation/Slab | 8/30/2023 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 2/26/2024 | Not Ready for Inspection | RICHARD DOCKUS |
| Wood Frame | 2/26/2024 | Corrections Issued | RICHARD DOCKUS |
| ELECTRICAL-Rough | 3/20/2024 | Partial Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 3/20/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/20/2024 | Partial Inspection | JOSEPH MCGARRY |
| Wood Frame | 3/20/2024 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 3/28/2024 | No Access for Inspection | RICHARD DOCKUS |
| HVAC-Rough | 3/28/2024 | No Access for Inspection | RICHARD DOCKUS |
| Interior/Exterior Lathing | 3/28/2024 | No Access for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 3/28/2024 | No Access for Inspection | RICHARD DOCKUS |
| Wood Frame | 3/28/2024 | No Access for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Rough | 3/29/2024 | Corrections Issued | BRIAN SULLIVAN |
| HVAC-Rough | 3/29/2024 | Corrections Issued | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 3/29/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 3/29/2024 | Conditional Approval | BRIAN SULLIVAN |
| Wood Frame | 3/29/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 4/3/2024 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 4/3/2024 | Approved | RAUL BARAJAS |
| HVAC-Rough | 4/3/2024 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 4/3/2024 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 4/3/2024 | Approved | RAUL BARAJAS |
| Insulation | 4/8/2024 | Approved | RAUL BARAJAS |
| Shower Pan | 4/8/2024 | Corrections Issued | RAUL BARAJAS |
| Shower Pan | 4/9/2024 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 4/11/2024 | Approved | RAUL BARAJAS |
| Drywall Nailing | 4/12/2024 | Approved | RAUL BARAJAS |
| Final | 2/27/2025 | Corrections Issued | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 2/27/2025 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 2/27/2025 | Approved | RAUL BARAJAS |
| Final | 3/6/2025 | Permit Finaled | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 3/6/2025 | SGSOV Approved | ROY SPAULDING |