2438 N LYRIC AVE 90027
Certificate Information: 2438 N LYRIC AVE 90027
- Application / Permit
- 22016-10000-35214
- Plan Check / Job No.
- B22LA23574
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: REMODEL TO (E) 2-STORY SFD TO REMODEL (E) KITCHEN , ADD NEW WINDOWS, REMOVE AND ADD DOORS, REMODEL (E) BATHROOMS, ADD SKYLIGHTS, REPLACE GUARDRAIL ON BALCONY ON 2ND FLOOR, REMOVE BALCONY ON FIRST FLOOR
- Permit Issued
- Issued on 11/7/2023
- Issuing Office
- Current Status
- Permit Finaled on 7/11/2025
Permit Application Status History
| Submitted | 11/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/28/2022 | LUISANGEL VALENZUELA |
| Corrections Issued | 11/29/2022 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 1/26/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 2/9/2023 | ALFRED RAMIREZ |
| No Progress | 11/1/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 11/1/2023 | ALFRED RAMIREZ |
| No Progress | 11/1/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 11/1/2023 | ALFRED RAMIREZ |
| No Progress | 11/2/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 11/2/2023 | ALFRED RAMIREZ |
| Issued | 11/7/2023 | APPLICANT |
| Permit Finaled | 7/10/2025 | ENRIQUE MIRELES |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/26/2023 | LUISANGEL VALENZUELA |
Contact Information
| Architect | Cooke,, Barrett H; Lic. No.: NA37365 | , |
| Contractor | Zorzoli Construction Inc; Lic. No.: 965210-B | , |
| Engineer | Rhee,, Kyle; Lic. No.: NA78215 | , |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/15/2023 | Approved | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 2/16/2024 | Conditional Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 3/20/2024 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 3/20/2024 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 3/20/2024 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 3/20/2024 | Approved | ENRIQUE MIRELES |
| Insulation | 3/29/2024 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 4/8/2024 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 5/22/2024 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 6/4/2024 | Corrections Issued | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 6/7/2024 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 5/12/2025 | Approved | ENRIQUE MIRELES |
| Final | 5/12/2025 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Final | 5/12/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 5/12/2025 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 5/12/2025 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 5/12/2025 | Approved | ENRIQUE MIRELES |
| Final | 7/10/2025 | Permit Finaled | ENRIQUE MIRELES |