455 N BARRINGTON AVE 90049

Certificate Information: 455 N BARRINGTON AVE 90049

Application / Permit
22016-10000-35210
Plan Check / Job No.
B22LA23569
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN- INTERIOR REMODEL TO CREATE A VAULTED CEILING AT (E) DINING ROOM, LIVING ROOM, BEDROOM AND MASTER BEDROOM AND REMODEL TO CREATE (N) BATHRROM, MOVE MASTER BEDROOM, CREATE (N) BEDROOM, CREATE LAUNDRY ROOM, AND REMODEL (E) BEDROOM, KITCHEN AND BATHROOM. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 1/17/2023
Issuing Office
Current Status
Permit Finaled on 5/10/2024

Permit Application Status History

Submitted 11/21/2022 APPLICANT
Assigned to Plan Check Engineer 11/28/2022 OMAR GARNICA
Corrections Issued 11/29/2022 OMAR GARNICA
Plan Check Approved 1/16/2023 OMAR GARNICA
Issued 1/17/2023 APPLICANT
Permit Finaled 5/9/2024 CARLOS MATAMOROS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/27/2022 ROBERT HUGHES
Eng Process Fee Ord 176,300 Cleared 1/4/2023 AHMED AMARRAGY
Sewer availability Cleared 1/4/2023 AHMED AMARRAGY

Contact Information

Architect Woodcraft,, Lawrence Albert; Lic. No.: NA23651       ,
Contractor R B Remodeling & Construction; Lic. No.: 905605-B       ,
Engineer Tan,, Henreik Steven; Lic. No.: NA65723       ,

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/1/2023 Partial Approval CARLOS MATAMOROS
Deputy Drilled-In Anchors 5/4/2023 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 5/5/2023 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 5/5/2023 Approved CARLOS MATAMOROS
PLUMBING-Rough 7/6/2023 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 8/21/2023 Approved CARLOS MATAMOROS
HVAC-Rough 8/21/2023 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 8/28/2023 Partial Approval STEPHANIE SWANSON
Insulation 8/28/2023 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 9/8/2023 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 9/8/2023 Approved CARLOS MATAMOROS
Insulation 9/8/2023 Approved CARLOS MATAMOROS
Drywall Nailing 9/20/2023 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 12/14/2023 Approved CARLOS MATAMOROS
Shower Pan 12/14/2023 Approved CARLOS MATAMOROS
Final 5/6/2024 Corrections Issued CARLOS MATAMOROS
Green Building Final 5/6/2024 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 5/6/2024 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 5/6/2024 Approved CARLOS MATAMOROS
Final 5/9/2024 Permit Finaled CARLOS MATAMOROS