127 E GALLEON ST 1-3 90292

Certificate Information: 127 E GALLEON ST 1-3 90292

Application / Permit
22016-10000-35125
Plan Check / Job No.
B22LA23505
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT EXISTING 347 SF 1ST FLOOR RECREATION ROOM TO AN ACCESSORY DWELLING UNIT. ATTACHED PER ORDINANCE
Permit Issued
Issued on 4/5/2023
Issuing Office
Current Status
CofO Issued on 9/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2022 APPLICANT
Assigned to Plan Check Engineer 12/15/2022 CARLOS MONTES
Corrections Issued 12/22/2022 CARLOS MONTES
Quality Review Completed 12/22/2022 GARO TELMI
Plan Check Approved 3/3/2023 CARLOS MONTES
Issued 4/5/2023 APPLICANT
CofO in Progress 8/29/2023 HERBERT GIRON
Permit Finaled 9/5/2023 DANIEL ORRANTE
CofO Issued 9/5/2023 DANIEL ORRANTE
Permit Finaled 9/5/2023 DANIEL ORRANTE

Permit Application Clearance Information

Highway dedication Cleared 1/3/2023 JASON NG
Eng Process Fee Ord 176,300 Cleared 1/5/2023 AHMED AMARRAGY
Miscellaneous Cleared 1/10/2023 RUBEN VASQUEZ
Miscellaneous Cleared 1/10/2023 RUBEN VASQUEZ
Miscellaneous Cleared 1/10/2023 RUBEN VASQUEZ
ZA Case Cleared 1/10/2023 RUBEN VASQUEZ
Specific Plan Cleared 1/12/2023 PEDRO AYALA
Specific Plan Cleared 1/12/2023 PEDRO AYALA
Address approval Cleared 1/17/2023 AHMED AMARRAGY
Coastal Zone Cleared 2/24/2023 RUBEN VASQUEZ
Coastal Zone Cleared 2/24/2023 RUBEN VASQUEZ
Frnt yard landscape/Water mgmt Cleared 2/24/2023 RUBEN VASQUEZ
Miscellaneous Cleared 2/24/2023 RUBEN VASQUEZ
Specific Plan Cleared 2/24/2023 RUBEN VASQUEZ

Contact Information

Architect Driscoll,, Christopher; Lic. No.: NA36073       ,
Contractor Barba Construction Inc; Lic. No.: 987160-B       ,

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Final 4/13/2023 Corrections Issued EVAN COOPER
SGSOV-Seismic Gas S/O Valve 4/13/2023 SGSOV Not Ready EVAN COOPER
Drywall Nailing 6/14/2023 Corrections Issued EVAN COOPER
Final 6/14/2023 Corrections Issued EVAN COOPER
Insulation 6/14/2023 Corrections Issued EVAN COOPER
Interior/Exterior Lathing 6/14/2023 Corrections Issued EVAN COOPER
Pre-Inspection 6/14/2023 Corrections Issued EVAN COOPER
SGSOV-Seismic Gas S/O Valve 6/14/2023 SGSOV Not Ready EVAN COOPER
Special/Order Compliance 6/14/2023 Corrections Issued EVAN COOPER
Wood Frame 6/14/2023 Corrections Issued EVAN COOPER
Final 8/18/2023 Corrections Issued HERBERT GIRON
Green Building Final 8/18/2023 Corrections Issued HERBERT GIRON
Green Building Rough 8/18/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 8/18/2023 SGSOV Not Required HERBERT GIRON
Smoke Detectors 8/18/2023 Approved HERBERT GIRON
Wood Frame 8/18/2023 Approved HERBERT GIRON
Final 8/28/2023 OK to Issue CofO HERBERT GIRON
Green Building Final 8/28/2023 Approved HERBERT GIRON