433 1/2 N LAUREL AVE 90048
Certificate Information: 433 1/2 N LAUREL AVE 90048
- Application / Permit
- 22016-10000-35106
- Plan Check / Job No.
- B22LA23479
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). NFPA 13D FIRE SPRINKLERS THROUGH OUT
- Permit Issued
- Issued on 8/6/2024
- Issuing Office
- Current Status
- CofO Issued on 2/14/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 12/24/2022 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 4/17/2023 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 7/14/2023 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 11/16/2023 | JAD BASMA |
| Plan Check Approved | 11/29/2023 | ALEC MOUSAKHANIAN |
| No Progress | 2/8/2024 | JEROME MAGAT PALMA |
| Plan Check Approved | 8/6/2024 | JEROME MAGAT PALMA |
| No Progress | 8/6/2024 | JEROME MAGAT PALMA |
| Plan Check Approved | 8/6/2024 | JEROME MAGAT PALMA |
| Issued | 8/6/2024 | APPLICANT |
| CofO in Progress | 2/9/2026 | JOSH MEISTER |
| Permit Finaled | 2/14/2026 | DEROLD HAUFF |
| Permit Finaled | 2/14/2026 | DEROLD HAUFF |
| CofO Issued | 2/14/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/3/2023 | AMAAN MALIK |
| Sewer availability | Cleared | 1/3/2023 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2023 | AMAAN MALIK |
| ZI | Cleared | 1/6/2023 | DANIEL CORONADO |
| Construction near power lines | Cleared | 4/6/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 4/6/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/19/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Footing/Foundation/Slab | 8/19/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Excavation/Setback/Form/Re-Bar | 8/20/2024 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 8/20/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 8/23/2024 | Corrections Issued | AMIR NAZARIAN |
| Footing/Foundation/Slab | 8/23/2024 | Corrections Issued | AMIR NAZARIAN |
| Special/Order Compliance | 8/23/2024 | Partial Approval | NICHOLAS LOPEZ |
| Excavation/Setback/Form/Re-Bar | 8/30/2024 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 8/30/2024 | Approved | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 9/3/2024 | Conditional Approval | JOSE MACIAS |
| Pre-Inspection | 9/12/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2024 | Approved | JOSE MACIAS |
| METHANE-Rough | 10/16/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 10/16/2024 | Partial Approval | JOSE MACIAS |
| Sewer | 10/16/2024 | Partial Approval | JOSE MACIAS |
| Sewer | 10/22/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 11/18/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 3/20/2025 | Not Ready for Inspection | JOSE MACIAS |
| Green Building Rough | 3/20/2025 | Not Ready for Inspection | JOSE MACIAS |
| PLUMBING-Rough | 3/20/2025 | Corrections Issued | JOSE MACIAS |
| Interior/Exterior Lathing | 3/27/2025 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 3/27/2025 | Approved | JOSE MACIAS |
| Service/Power Release | 3/27/2025 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 4/1/2025 | Approved | JOSE MACIAS |
| Green Building Rough | 4/1/2025 | Approved | JOSE MACIAS |
| Insulation | 4/1/2025 | Approved | JOSE MACIAS |
| Insulation | 4/3/2025 | Approved | JOSE MACIAS |
| Drywall Nailing | 4/15/2025 | Approved | JOSE MACIAS |
| Shower Pan | 4/18/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 4/29/2025 | Approved | ALEX COLIN |
| Final | 1/16/2026 | Corrections Issued | JOSH MEISTER |
| Green Building Final | 1/16/2026 | Not Ready for Inspection | JOSH MEISTER |
| SGSOV-Seismic Gas S/O Valve | 1/16/2026 | SGSOV Approved | JOSH MEISTER |
| Smoke Detectors | 1/16/2026 | Approved | JOSH MEISTER |
| Final | 2/6/2026 | OK to Issue CofO | JOSH MEISTER |
| Green Building Final | 2/6/2026 | Approved | JOSH MEISTER |