10310 S WALL ST 90003
Certificate Information: 10310 S WALL ST 90003
- Application / Permit
- 22016-10000-35098
- Plan Check / Job No.
- B22LA23469
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing 20' x 20' detached garage into a new detached accessory dwelling unit (400 s.f) per LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 10/4/2023
- Issuing Office
- Current Status
- CofO Issued on 4/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/7/2022 | ISIS ARGUETA |
| Corrections Issued | 12/9/2022 | ISIS ARGUETA |
| Applicant returned to address corrections | 1/19/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 4/20/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 4/27/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 5/18/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 6/1/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 7/26/2023 | MIROOSH KHACHATOORIAN |
| Issued | 10/4/2023 | APPLICANT |
| CofO in Progress | 4/18/2025 | ANSON MAGLASANG |
| Permit Finaled | 4/18/2025 | ANSON MAGLASANG |
| CofO Issued | 4/18/2025 | ANSON MAGLASANG |
| Permit Finaled | 4/18/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 12/29/2022 | CELINA MORENO |
| Sewer availability | Cleared | 12/29/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 1/5/2023 | CELINA MORENO |
| Construction near power lines | Cleared | 4/14/2023 | RIDWAN HARDY |
Contact Information
| Contractor | E & E Builders Inc; Lic. No.: 1060959-B | , |
| Engineer | Grandhi,, Venkata Rohit; Lic. No.: C88709 | 7823 BOXWOOD CT HIGHLAND, CA 92346 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 10/24/2023 | Approved | JAMES CHAVEZ |
| Underground Mechanical | 10/24/2023 | Partial Approval | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 11/15/2023 | No Access for Inspection | JOHN KLARIN |
| ELECTRICAL-Rough | 11/15/2023 | No Access for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 11/15/2023 | No Access for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 11/17/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 11/29/2023 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 11/29/2023 | Corrections Issued | JOHN KLARIN |
| Wood Frame | 11/29/2023 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 12/5/2023 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 12/15/2023 | No Access for Inspection | JOHN KLARIN |
| ELECTRICAL-Rough | 12/20/2023 | Not Ready for Inspection | JOHN KLARIN |
| Footing/Foundation/Slab | 12/20/2023 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 2/7/2024 | Corrections Issued | BEN MOLSTAD |
| Wood Frame | 2/7/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Footing/Foundation/Slab | 2/15/2024 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 2/16/2024 | No Access for Inspection | JAMES CHAVEZ |
| Footing/Foundation/Slab | 2/26/2024 | Corrections Issued | BEN MOLSTAD |
| BUILDING-Rough-Frame | 3/13/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 3/13/2024 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Rough | 3/13/2024 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 5/6/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 5/6/2024 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 5/6/2024 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Rough | 5/15/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| PLUMBING-Rough | 5/15/2024 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Rough | 5/21/2024 | Corrections Issued | BEN MOLSTAD |
| Light Gage Steel Frame | 5/21/2024 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Rough | 5/21/2024 | Corrections Issued | BEN MOLSTAD |
| BUILDING-Rough-Frame | 8/22/2024 | Corrections Issued | BEN MOLSTAD |
| Special/Order Compliance | 8/22/2024 | Partial Inspection | BARRY HACHE |
| BUILDING-Rough-Frame | 8/29/2024 | Approved | ANSON MAGLASANG |
| Drywall Nailing | 9/6/2024 | Corrections Issued | BARRY HACHE |
| Drywall Nailing | 9/12/2024 | Approved | ANSON MAGLASANG |
| ELECTRICAL-Final | 12/16/2024 | No Access for Inspection | ANSON MAGLASANG |
| Final | 12/16/2024 | No Access for Inspection | ANSON MAGLASANG |
| HVAC-Final | 12/16/2024 | No Access for Inspection | ANSON MAGLASANG |
| PLUMBING-Final | 12/16/2024 | No Access for Inspection | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 12/16/2024 | SGSOV Not Ready | ANSON MAGLASANG |
| Smoke Detectors | 12/16/2024 | No Access for Inspection | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 12/20/2024 | SGSOV Not Ready | ANTHONY EGSON |
| ELECTRICAL-Final | 1/7/2025 | Corrections Issued | ANTHONY EGSON |
| Final | 1/7/2025 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 1/7/2025 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 1/7/2025 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 1/7/2025 | SGSOV Not Required | ANTHONY EGSON |
| Smoke Detectors | 1/7/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 1/10/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 1/10/2025 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 1/10/2025 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 1/10/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 3/18/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 3/18/2025 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 3/18/2025 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 3/18/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 4/2/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 4/2/2025 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 4/2/2025 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 4/2/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 4/18/2025 | Approved | ANSON MAGLASANG |
| Final | 4/18/2025 | OK to Issue CofO | ANSON MAGLASANG |
| HVAC-Final | 4/18/2025 | Approved | ANSON MAGLASANG |
| PLUMBING-Final | 4/18/2025 | Approved | ANSON MAGLASANG |