8333 S GONZAGA AVE 90045
Certificate Information: 8333 S GONZAGA AVE 90045
- Application / Permit
- 22016-10000-35085
- Plan Check / Job No.
- B22LA23465
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPlan: Conversion of Garage and Storage Room to ADU per GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 6/19/2023
- Issuing Office
- Current Status
- CofO Issued on 1/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/29/2022 | DAVID CASTILLO |
| Corrections Issued | 11/30/2022 | DAVID CASTILLO |
| Plan Check Approved | 6/14/2023 | ANDREW SANTIAGO |
| Issued | 6/19/2023 | APPLICANT |
| CofO in Progress | 1/16/2025 | TEMISTOCLES CAAL |
| Permit Finaled | 1/16/2025 | RICHARD STEINBACH |
| CofO Issued | 1/16/2025 | RICHARD STEINBACH |
| Permit Finaled | 1/16/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 2/1/2023 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2023 | JENSON LEE |
| Sewer availability | Cleared | 2/1/2023 | JENSON LEE |
| Grading Pre-Inspection | Cleared | 2/6/2023 | KIRK LINKLATER |
| Specific Plan | Cleared | 2/21/2023 | EDUARDO HERMOSO |
| Low Impact Development | Cleared | 5/22/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 5/24/2023 | LIAM ODONOVAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
| Engineer | Truong,, Phong; Lic. No.: NA70784 | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/27/2023 | Partial Inspection | BOBBY KEY |
| PLUMBING-Rough | 12/29/2023 | Partial Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 1/4/2024 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 1/8/2024 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 4/18/2024 | Not Ready for Inspection | RICHARD STEINBACH |
| ELECTRICAL-Rough | 4/18/2024 | Approved | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2024 | Partial Approval | RICHARD STEINBACH |
| Green Building Rough | 4/18/2024 | Not Ready for Inspection | RICHARD STEINBACH |
| HVAC-Rough | 4/18/2024 | Corrections Issued | RICHARD STEINBACH |
| PLUMBING-Rough | 4/18/2024 | Approved | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 5/31/2024 | No Access for Inspection | BOBBY KEY |
| Green Building Rough | 5/31/2024 | No Access for Inspection | BOBBY KEY |
| HVAC-Rough | 5/31/2024 | No Access for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 5/31/2024 | No Access for Inspection | BOBBY KEY |
| HVAC-Rough | 6/3/2024 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 6/3/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 6/13/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 6/13/2024 | Partial Approval | BOBBY KEY |
| Special/Order Compliance | 6/13/2024 | Corrections Issued | BOBBY KEY |
| Insulation | 8/2/2024 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 8/14/2024 | Approved | BOBBY KEY |
| Green Building Rough | 8/14/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 8/27/2024 | Approved | BOBBY KEY |
| Gas Test | 9/19/2024 | Conditional Approval | BOBBY KEY |
| Interior/Exterior Lathing | 9/19/2024 | Approved | BOBBY KEY |
| Sewer | 9/19/2024 | Approved | BOBBY KEY |
| Shower Pan | 9/19/2024 | Approved | BOBBY KEY |
| Underground Mechanical | 9/19/2024 | Corrections Issued | BOBBY KEY |
| Underground Mechanical | 10/18/2024 | Corrections Issued | BOBBY KEY |
| Underground Mechanical | 10/25/2024 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Final | 11/15/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Final | 11/15/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Service/Power Release | 11/15/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 12/18/2024 | Corrections Issued | MICHAEL ALLEN |
| Gas Test | 12/18/2024 | Approved | MICHAEL ALLEN |
| HVAC-Final | 12/18/2024 | Corrections Issued | MICHAEL ALLEN |
| PLUMBING-Final | 12/18/2024 | Approved | MICHAEL ALLEN |
| Special/Order Compliance | 12/18/2024 | Corrections Issued | MICHAEL ALLEN |
| Final | 1/15/2025 | OK to Issue CofO | TEMISTOCLES CAAL |
| Green Building Final | 1/15/2025 | Approved | TEMISTOCLES CAAL |
| METHANE-Final | 1/15/2025 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 1/15/2025 | SGSOV Approved | TEMISTOCLES CAAL |
| Service/Power Release | 1/15/2025 | Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 1/15/2025 | Approved | TEMISTOCLES CAAL |