5424 W LEMON GROVE AVE 90038
Certificate Information: 5424 W LEMON GROVE AVE 90038
- Application / Permit
- 22016-10000-35083
- Plan Check / Job No.
- B22LA23462
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 1/26/2023
- Issuing Office
- Current Status
- CofO Issued on 8/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/23/2022 | DANIEL YIP |
| Corrections Issued | 11/27/2022 | DANIEL YIP |
| Applicant returned to address corrections | 12/29/2022 | DANIEL YIP |
| Plan Check Approved | 1/3/2023 | DANIEL YIP |
| Issued | 1/26/2023 | APPLICANT |
| CofO in Progress | 5/9/2024 | JEFFREY MEAD |
| CofO Issued | 8/5/2024 | DEROLD HAUFF |
| Permit Finaled | 8/5/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/29/2022 | WALLIE JONG |
| Sewer availability | Cleared | 11/29/2022 | WALLIE JONG |
| Tenant Habitability Plan | Cleared | 12/5/2022 | ISMAEL HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2023 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/14/2023 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 10/19/2023 | Corrections Issued | JEFFREY MEAD |
| ELECTRICAL-Rough | 10/19/2023 | Approved | JEFFREY MEAD |
| HVAC-Rough | 10/19/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 10/19/2023 | Approved | JEFFREY MEAD |
| Wood Frame | 10/30/2023 | Corrections Issued | JEFFREY MEAD |
| BUILDING-Rough-Frame | 12/15/2023 | Partial Approval | JEFFREY MEAD |
| Insulation | 1/17/2024 | Approved | JEFFREY MEAD |
| Drywall Nailing | 1/26/2024 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 1/26/2024 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 4/24/2024 | Partial Approval | JEFFREY MEAD |
| ELECTRICAL-Final | 4/24/2024 | Corrections Issued | JEFFREY MEAD |
| Final | 4/24/2024 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 4/24/2024 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 4/24/2024 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 4/24/2024 | SGSOV Not Required | JEFFREY MEAD |
| Smoke Detectors | 4/24/2024 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 5/2/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 5/2/2024 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 5/8/2024 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 5/8/2024 | Approved | JEFFREY MEAD |
| Final | 5/8/2024 | OK to Issue CofO | JEFFREY MEAD |
| Special/Order Compliance | 7/1/2024 | Corrections Issued | JEFFREY MEAD |