2621 W 76TH ST 90043

Certificate Information: 2621 W 76TH ST 90043

Application / Permit
22016-10000-34974
Plan Check / Job No.
B22LA23386
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED BATHROOM REMODEL. CONST. PER W.F.P.P.
Permit Issued
Issued on 12/1/2022
Issuing Office
Metro
Current Status
Permit Finaled on 2/3/2023

Permit Application Status History

Submitted 11/18/2022 APPLICANT
Assigned to Plan Check Engineer 11/18/2022 LAWRENCE QUIRANTE
Plan Check Approved 11/18/2022 LAWRENCE QUIRANTE
Issued 12/1/2022 APPLICANT
Permit Finaled 2/2/2023 ENRIQUE MIRELES

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Copper Canyon Construction Inc; Lic. No.: 1045482-B 6146 MAIN STREET      SOUTH GATE, CA 90280

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/7/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 12/12/2022 Corrections Issued ENRIQUE MIRELES
PLUMBING-Rough 12/13/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 12/27/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 12/27/2022 Approved ENRIQUE MIRELES
HVAC-Rough 12/27/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 12/27/2022 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 12/27/2022 Approved ENRIQUE MIRELES
Insulation 12/30/2022 Approved ENRIQUE MIRELES
Shower Pan 12/30/2022 Approved ENRIQUE MIRELES
Drywall Nailing 1/4/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 1/4/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Final 2/2/2023 Approved ENRIQUE MIRELES
Final 2/2/2023 Permit Finaled ENRIQUE MIRELES
Gas Test 2/2/2023 Approved ENRIQUE MIRELES
HVAC-Final 2/2/2023 Approved ENRIQUE MIRELES
PLUMBING-Final 2/2/2023 Approved ENRIQUE MIRELES
Smoke Detectors 2/2/2023 Approved ENRIQUE MIRELES