1231 N SPRING ST 90012
Certificate Information: 1231 N SPRING ST 90012
- Application / Permit
- 22016-10000-34825
- Plan Check / Job No.
- B22LA23266
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- EPLAN A TENANT IMPROVEMENT (TI) TO EXISTING CORE AND SHELL BUILDINGS. THE PROJECT WILL OCCUPY PORTIONS OF LEVELS 02, LEVEL 02 MEZZANINE, AND LEVEL 03 OF THE EXISTING BUILDINGS. THE PROJECT WILL BE AN OFFICE SPACE CONSISTING OF OPEN WORK SPACE, ENCLOSED MEETING ROOMS, AND SHARED AMMENITY SPACES. INTERIOR IMPROVEMENTS ONLY. THERE WILL BE NO CHANGE TO BUILDING STRUCTURE AND NO NEW AREA ADDED
- Permit Issued
- Issued on 12/16/2022
- Issuing Office
- Current Status
- Permit Finaled on 8/10/2023
Permit Application Status History
| Submitted | 11/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/23/2022 | FERNANDO FLORES |
| Corrections Issued | 11/29/2022 | FERNANDO FLORES |
| Plan Check Approved | 12/13/2022 | FERNANDO FLORES |
| Issued | 12/16/2022 | APPLICANT |
| Permit Finaled | 8/10/2023 | JULIAN CAPUCETTI |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 12/5/2022 | DAVID URITA |
| Historic monument | Cleared | 12/5/2022 | MAX LODER |
| Redevelopment Project Area | Cleared | 12/5/2022 | DAVID URITA |
Contact Information
| Contractor | G C X Llc; Lic. No.: 1045286-B | , |
| Engineer | Tan,, Charles; Lic. No.: NA4758 | , |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 3/24/2023 | Partial Approval | JULIAN CAPUCETTI |
| Deputy Steel/Welding | 3/31/2023 | Conditional Approval | JULIAN CAPUCETTI |
| Drywall Nailing | 4/3/2023 | Approved | JULIAN CAPUCETTI |
| Insulation | 4/3/2023 | Approved | JULIAN CAPUCETTI |
| Structural Steel Frame | 4/3/2023 | Approved | JULIAN CAPUCETTI |
| Drywall Nailing | 4/11/2023 | Approved | JULIAN CAPUCETTI |
| Light Gage Steel Frame | 4/11/2023 | Partial Approval | JULIAN CAPUCETTI |
| Light Gage Steel Frame | 4/25/2023 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 4/27/2023 | Partial Approval | RAFAEL CORTES |
| Light Gage Steel Frame | 5/8/2023 | Approved | JULIAN CAPUCETTI |
| T-Bar Ceiling | 5/8/2023 | Approved | JULIAN CAPUCETTI |
| Light Gage Steel Frame | 6/28/2023 | Approved | JULIAN CAPUCETTI |
| Final | 8/10/2023 | Permit Finaled | JULIAN CAPUCETTI |
| Green Building Final | 8/10/2023 | Approved | JULIAN CAPUCETTI |
| SGSOV-Seismic Gas S/O Valve | 8/10/2023 | SGSOV Approved | JULIAN CAPUCETTI |
| Smoke Detectors | 8/10/2023 | Approved | JULIAN CAPUCETTI |