1538 S ESPERANZA ST 90023
Certificate Information: 1538 S ESPERANZA ST 90023
- Application / Permit
- 22016-10000-34618
- Plan Check / Job No.
- B22LA23104
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Nursery plant
- Work Description
- CHANGE OF USE FROM SHEET METAL FACTORY TO INDOOR PLANT CULTIVATION.
- Permit Issued
- Issued on 7/20/2023
- Issuing Office
- Current Status
- Issued on 7/20/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/17/2022 | ARMEN JIVALAGIAN |
| Corrections Issued | 11/22/2022 | ARMEN JIVALAGIAN |
| Quality Review Completed | 11/22/2022 | PETER KIM |
| Applicant returned to address corrections | 12/13/2022 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 6/25/2023 | ARMEN JIVALAGIAN |
| Plan Check Approved | 6/28/2023 | ARMEN JIVALAGIAN |
| Issued | 7/20/2023 | APPLICANT |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 12/21/2022 | JASON CHAN |
| Historic Resource Verification | Cleared | 12/29/2022 | DAVID URITA |
| Redevelopment Project Area | Cleared | 12/29/2022 | DAVID URITA |
| Construction near power lines | Cleared | 2/17/2023 | OSCAR CASTRO |
| Construction within easement | Cleared | 2/17/2023 | OSCAR CASTRO |
| Miscellaneous | Cleared | 4/25/2023 | VIDAL GARCIA |
| DAS Clearance | Cleared | 5/17/2023 | Ricardo Ramirez Solis |
| Green Code | Cleared | 5/25/2023 | AARON COSTA |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 6/13/2023 | TREVOR QUAN |
Contact Information
| Architect | Seo,, Hyung Jin; Lic. No.: NA31053 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 9/12/2023 | Approved | ALAN MORELOS |
| Wood Frame | 9/12/2023 | Not Ready for Inspection | ALAN MORELOS |
| Special/Order Compliance | 10/22/2024 | Approved | RONALD JIMENEZ |
| Wood Frame | 3/12/2026 | Partial Approval | IAN BLINN |