712 N SEWARD ST 90038

Certificate Information: 712 N SEWARD ST 90038

Application / Permit
22016-10000-34502
Plan Check / Job No.
B22LA23024
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
ePLAN- Office tenant improvement to existing Type VB two-story building. No change of use proposed.
Permit Issued
Issued on 4/7/2023
Issuing Office
Current Status
CofO Issued on 4/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/16/2022 APPLICANT
Assigned to Plan Check Engineer 12/8/2022 JOHNNY WU
Corrections Issued 12/30/2022 JOHNNY WU
Quality Review Completed 1/4/2023 RODOLFO ARIAS
Applicant returned to address corrections 3/15/2023 JOHNNY WU
Applicant returned to address corrections 3/17/2023 JOHNNY WU
Applicant returned to address corrections 4/7/2023 JOHNNY WU
Plan Check Approved 4/7/2023 JOHNNY WU
Issued 4/7/2023 APPLICANT
CofO Issued 4/11/2024 WINSTON DUNNING
Permit Finaled 4/11/2024 WINSTON DUNNING

Permit Application Clearance Information

Green Code Cleared 3/15/2023 Jesse Jimenez
DAS Clearance Cleared 4/7/2023 Jesse Jimenez

Contact Information

Architect House,, James Douglas; Lic. No.: NA15526       ,
Contractor Warner Constructors Llc; Lic. No.: 528146-B       ,
Engineer Smith,, Chris Wayne; Lic. No.: NA6106       ,

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 4/27/2023 Partial Approval RONALD JIMENEZ
Drywall Nailing 5/3/2023 Not Ready for Inspection VAHE KELEDJIAN
Insulation 5/3/2023 Partial Approval VAHE KELEDJIAN
Drywall Nailing 5/12/2023 Partial Approval RONALD JIMENEZ
Deputy Wood Construction 5/22/2023 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 6/1/2023 Partial Approval RONALD JIMENEZ
Green Building Rough 6/26/2023 Approved MARTIN TAVITIAN
METHANE-Rough 6/26/2023 Approved MARTIN TAVITIAN
Wood Frame 6/26/2023 Partial Approval MARTIN TAVITIAN
Drywall Nailing 7/25/2023 Approved RONALD JIMENEZ
T-Bar Ceiling 7/25/2023 Not Ready for Inspection RONALD JIMENEZ
Light Gage Steel Frame 8/24/2023 Partial Approval RONALD JIMENEZ
Deputy Reinf. Concrete 10/10/2023 Conditional Approval ERNESTO CORRAL
Final 11/17/2023 Partial Inspection RONALD JIMENEZ
Green Building Final 11/17/2023 Not Ready for Inspection RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 11/17/2023 SGSOV Not Ready RONALD JIMENEZ
Smoke Detectors 11/17/2023 Approved RONALD JIMENEZ
Wood Frame 11/17/2023 Partial Inspection RONALD JIMENEZ
Final 2/8/2024 Conditional Approval JACOB MYERS
Green Building Final 2/8/2024 Approved JACOB MYERS
SGSOV-Seismic Gas S/O Valve 2/8/2024 SGSOV No Gas JACOB MYERS
Wood Frame 2/8/2024 Approved JACOB MYERS