1432 S ELLSMERE AVE 90019
Certificate Information: 1432 S ELLSMERE AVE 90019
- Application / Permit
- 22016-10000-34083
- Plan Check / Job No.
- B22LA22749
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePLAN- MAJOR REMODEL. Interior remodel of single family 1-story residence with attached garage.
- Permit Issued
- Issued on 9/18/2023
- Issuing Office
- Current Status
- Issued on 9/18/2023
Permit Application Status History
| Submitted | 11/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2022 | ARSALAN SHABESTARI |
| Corrections Issued | 11/13/2022 | ARSALAN SHABESTARI |
| Quality Review Completed | 11/21/2022 | FARUK SEZER |
| Plan Check Approved | 1/4/2023 | ARSALAN SHABESTARI |
| Issued | 9/18/2023 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/9/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 12/9/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2022 | TREVOR QUAN |
Contact Information
| Contractor | Orozco Ulises; Lic. No.: 925739-B | , |
| Engineer | Le,, Thang Huu; Lic. No.: NA4978 | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/30/2023 | Conditional Approval | JOSE AVILA |
| Footing/Foundation/Slab | 12/1/2023 | Corrections Issued | STUART CHAPMAN |
| Deputy Reinf. Concrete | 3/26/2024 | Conditional Approval | JOSH MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2024 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 4/3/2024 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 4/3/2024 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 4/3/2024 | Not Ready for Inspection | RICHARD DOCKUS |
| Interior/Exterior Lathing | 4/10/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 4/10/2024 | Approved | JOSEPH MCGARRY |
| Wood Frame | 4/11/2024 | Corrections Issued | RICHARD DOCKUS |
| Insulation | 4/16/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Insulation | 4/18/2024 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 4/26/2024 | Corrections Issued | AMIR NAZARIAN |
| Final | 7/1/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| METHANE-Final | 7/1/2024 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 7/1/2024 | SGSOV Approved | ARTHUR NEGRETE |
| Smoke Detectors | 7/1/2024 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 7/10/2024 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Final | 7/10/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Final | 7/10/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Final | 7/18/2024 | Approved | ARTHUR NEGRETE |
| Final | 7/18/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| HVAC-Final | 7/18/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 7/18/2024 | Approved | ARTHUR NEGRETE |