6212 W COMMODORE SLOAT DR 90048
Certificate Information: 6212 W COMMODORE SLOAT DR 90048
- Application / Permit
- 22016-10000-34070
- Plan Check / Job No.
- B22LA22738
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Install Special Steel Cantilever Columns
- Permit Issued
- Issued on 6/6/2023
- Issuing Office
- Current Status
- CofC Issued on 3/21/2024
Permit Application Status History
| Submitted | 11/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/7/2022 | HANS SANTIAGO |
| Corrections Issued | 12/12/2022 | HANS SANTIAGO |
| Quality Review Completed | 12/14/2022 | LIPING TENG |
| Applicant returned to address corrections | 2/27/2023 | HANS SANTIAGO |
| Plan Check Approved | 5/4/2023 | ANDREW SANTIAGO |
| Issued | 6/6/2023 | APPLICANT |
| OK for CofC | 11/22/2023 | DARRYL ARNOLD |
| CofC Issued | 3/21/2024 | WINSTON DUNNING |
Permit Application Clearance Information
| City Hist. Cultural Monument | Cleared | 4/25/2023 | JONATHAN KAPLAN |
| HPOZ | Cleared | 4/25/2023 | JONATHAN KAPLAN |
| Tenant Habitability Plan | Cleared | 6/1/2023 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | American Retrofitters Corp; Lic. No.: 1020382-B | , |
| Engineer | Vartanian,, Albert; Lic. No.: C39989 | PO BOX 857 VERDUGO CITY, CA 91046 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/18/2023 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 11/3/2023 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 11/3/2023 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 11/3/2023 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 11/14/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| Drywall Nailing | 11/15/2023 | Approved | JACOB MYERS |
| Interior/Exterior Lathing | 11/15/2023 | Approved | JACOB MYERS |
| Final | 11/22/2023 | OK for CofC | DARRYL ARNOLD |
| METHANE-Final | 11/22/2023 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 11/22/2023 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 11/22/2023 | Approved | DARRYL ARNOLD |