5616 W SPOKANE ST 90016
Certificate Information: 5616 W SPOKANE ST 90016
- Application / Permit
- 22016-10000-33984
- Plan Check / Job No.
- B22LA22711
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN* INTERRIOR REMODEL OF EXISTING SINGLE FAMILY DWELLING - ALL WORK PER ENGINEER
- Permit Issued
- Issued on 5/23/2023
- Issuing Office
- Current Status
- Issued on 5/23/2023
Permit Application Status History
| Submitted | 11/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/15/2022 | DANIEL ABRAMYAN |
| Corrections Issued | 11/16/2022 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 12/14/2022 | DANIEL ABRAMYAN |
| Plan Check Approved | 12/22/2022 | DANIEL YIP |
| Issued | 5/23/2023 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Song,, Michael; Lic. No.: NA32566 | , |
| Contractor | Line George Construction; Lic. No.: 615352-B | , |
| Engineer | Rastegari,, Esmail Nader; Lic. No.: NA43332 | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/30/2023 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 5/30/2023 | Approved | JOSE AVILA |
| Deputy Drilled-In Anchors | 6/15/2023 | Conditional Approval | JOSE AVILA |
| ELECTRICAL-Rough | 6/15/2023 | Partial Approval | JOSE AVILA |
| HVAC-Rough | 6/15/2023 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 6/15/2023 | Corrections Issued | JOSE AVILA |
| Wood Frame | 6/15/2023 | Partial Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 6/27/2023 | Corrections Issued | JOSE AVILA |
| Gas Test | 6/27/2023 | Partial Approval | JOSE AVILA |
| HVAC-Rough | 6/27/2023 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 6/27/2023 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 7/6/2023 | Approved | JOSE AVILA |
| HVAC-Rough | 7/6/2023 | Approved | JOSE AVILA |
| Shower Pan | 7/6/2023 | Not Ready for Inspection | JOSE AVILA |
| Insulation | 7/17/2023 | Partial Approval | JOSE AVILA |
| Interior/Exterior Lathing | 7/17/2023 | Approved | JOSE AVILA |
| Shower Pan | 7/17/2023 | Approved | JOSE AVILA |
| Drywall Nailing | 7/20/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 7/20/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 10/12/2023 | Approved | STUART CHAPMAN |
| Final | 10/12/2023 | Corrections Issued | STUART CHAPMAN |
| HVAC-Final | 10/12/2023 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Final | 10/12/2023 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 10/12/2023 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 10/12/2023 | Approved | STUART CHAPMAN |