23950 W VANOWEN ST 91307
Certificate Information: 23950 W VANOWEN ST 91307
- Application / Permit
- 22016-10000-33905
- Plan Check / Job No.
- B22LA22657
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- interior and exterior altreation of existing one story single family dewlling per engineer design, deatils (no change in height or floor area) - remode kitchen, add skylight
- Permit Issued
- Issued on 1/5/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 3/15/2023
Permit Application Status History
| Submitted | 11/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2022 | AUNG SOE |
| Plan Check Approved | 11/8/2022 | AUNG SOE |
| Issued | 1/5/2023 | APPLICANT |
| Permit Finaled | 3/14/2023 | TROY SANDERS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Song,, Michael; Lic. No.: C32566 | 821 LIME AVENUE LONG BEACH, CA 90813 |
| Contractor | Better Together Builders Inc; Lic. No.: 1047689-B | 16430 VENTURA BLVD #304 ENCINO, CA 91436 |
| Engineer | Alson,, Ken; Lic. No.: C41697 | 9744 MAPLE ST 201 BELLFLOWER, CA 90706 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/6/2023 | Not Ready for Inspection | MORRIS JACKSON |
| ELECTRICAL-Rough | 1/6/2023 | Not Ready for Inspection | MORRIS JACKSON |
| HVAC-Rough | 1/6/2023 | Not Ready for Inspection | MORRIS JACKSON |
| PLUMBING-Rough | 1/6/2023 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 1/10/2023 | Partial Approval | TROY SANDERS |
| Rough-Elec/Plmb/HVAC | 1/10/2023 | Approved | TROY SANDERS |
| Insulation | 1/13/2023 | Corrections Issued | JESUS PINEDA |
| Interior/Exterior Lathing | 1/13/2023 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 1/19/2023 | Partial Approval | TROY SANDERS |
| Insulation | 1/19/2023 | Approved | TROY SANDERS |
| Special/Order Compliance | 1/19/2023 | Partial Inspection | MORRIS JACKSON |
| Drywall Nailing | 1/24/2023 | Approved | MORRIS JACKSON |
| Final | 3/3/2023 | Not Ready for Inspection | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 3/3/2023 | SGSOV Not Ready | TROY SANDERS |
| Smoke Detectors | 3/3/2023 | Not Ready for Inspection | TROY SANDERS |
| Final | 3/14/2023 | Permit Finaled | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 3/14/2023 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 3/14/2023 | Approved | TROY SANDERS |