1827 S CABRILLO AVE 1-5 90731

Certificate Information: 1827 S CABRILLO AVE 1-5 90731

Application / Permit
22016-10000-33660
Plan Check / Job No.
B22LA22490
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Convert existing basement space into new ADU. 644sqft in an (e) apartment building per GCS 65852.2(e)(1)(C)
Permit Issued
Issued on 7/8/2024
Issuing Office
Current Status
CofO Issued on 7/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2022 APPLICANT
Assigned to Plan Check Engineer 11/16/2022 JOSEPH RAFOLS
Corrections Issued 11/17/2022 JOSEPH RAFOLS
Plan Check Approved 3/21/2023 JOSEPH RAFOLS
Issued 7/8/2024 APPLICANT
CofO in Progress 6/23/2025 RICARDO ROBLES
Permit Finaled 7/1/2025 HENRY BAGHDASSARIAN
CofO Issued 7/1/2025 HENRY BAGHDASSARIAN
Permit Finaled 7/1/2025 HENRY BAGHDASSARIAN

Permit Application Clearance Information

Address approval Cleared 12/22/2022 ANA SORIANO
Eng Process Fee Ord 176,300 Cleared 1/31/2023 ANA SORIANO
Sewer availability Cleared 1/31/2023 ANA SORIANO
Tenant Habitability Plan Cleared 2/2/2023 MICHAEL SOTO
Grading Pre-Inspection Cleared 3/16/2023 JOSEPH RAFOLS

Contact Information

Contractor H T A Construction & Development; Lic. No.: 1044038-B       ,
Contractor Hta Construction & Development; Lic. No.: 1044038-B       ,
Engineer Shirley,, Peter; Lic. No.: C75050 4429 DAWES AVE      CULVER CITY, CA 90230

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 8/19/2024 Approved JOEY BUCHANAN
Pre-Inspection 8/19/2024 Corrections Issued AMANUEL BERHE
Smoke Detectors 1/22/2025 Corrections Issued MICHAEL PETRUSKO
Final 6/6/2025 Corrections Issued MICHAEL PETRUSKO
Green Building Final 6/6/2025 Not Ready for Inspection MICHAEL PETRUSKO
SGSOV-Seismic Gas S/O Valve 6/6/2025 SGSOV Not Ready MICHAEL PETRUSKO
Smoke Detectors 6/6/2025 Not Ready for Inspection MICHAEL PETRUSKO
Wood Frame 6/6/2025 Not Ready for Inspection MICHAEL PETRUSKO
Final 6/23/2025 OK to Issue CofO RICARDO ROBLES
Green Building Final 6/23/2025 Approved RICARDO ROBLES
SGSOV-Seismic Gas S/O Valve 6/23/2025 SGSOV Approved RICARDO ROBLES
Smoke Detectors 6/23/2025 Approved RICARDO ROBLES
Wood Frame 6/23/2025 Approved RICARDO ROBLES