4250 N ALONZO AVE 91316
Certificate Information: 4250 N ALONZO AVE 91316
- Application / Permit
- 22016-10000-33457
- Plan Check / Job No.
- B22LA22305
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: EXTERIOR AND INTERIOR REMODEL TO (E) 1-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
- Permit Issued
- Issued on 1/17/2023
- Issuing Office
- Current Status
- Permit Finaled on 5/24/2024
Permit Application Status History
| Submitted | 11/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/10/2022 | DANIEL YIP |
| Corrections Issued | 11/12/2022 | DANIEL YIP |
| Applicant returned to address corrections | 11/29/2022 | DANIEL YIP |
| Plan Check Approved | 1/6/2023 | ZAW HAN |
| Issued | 1/17/2023 | APPLICANT |
| Permit Finaled | 5/23/2024 | JOHN KIDWELL |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | We Design & Development Co; Lic. No.: 1058476-B | , |
| Engineer | Rezai,, Farhad; Lic. No.: NA3970 | , |
| Engineer | Rezai,, Farhad; Lic. No.: S3970 | 21102 COCOBANA LANE HUNTINGTON BEACH, CA 92646 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/31/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| Footing/Foundation/Slab | 1/31/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| Deputy Drilled-In Anchors | 2/1/2023 | Conditional Approval | JESUS PINEDA |
| Excavation/Setback/Form/Re-Bar | 2/2/2023 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 2/2/2023 | Approved | DAVID SANDOVAL |
| HVAC-Rough | 2/23/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 2/23/2023 | Corrections Issued | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 3/8/2023 | Partial Inspection | DAVID SANDOVAL |
| ELECTRICAL-Rough | 3/8/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| HVAC-Rough | 3/8/2023 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 3/8/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 3/10/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| Special/Order Compliance | 3/10/2023 | Partial Inspection | MORRIS JACKSON |
| PLUMBING-Rough | 3/16/2023 | Partial Approval | DAVID SANDOVAL |
| Gas Test | 4/10/2023 | Approved | MORRIS JACKSON |
| Pre-Inspection | 4/10/2023 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 5/19/2023 | Corrections Issued | SEAN HAUPT |
| Interior/Exterior Lathing | 5/19/2023 | Corrections Issued | SEAN HAUPT |
| Shower Pan | 5/19/2023 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 5/23/2023 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 5/23/2023 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 6/7/2023 | Approved | SEAN HAUPT |
| Insulation | 6/7/2023 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 6/9/2023 | Approved | MORRIS JACKSON |
| Shower Pan | 6/9/2023 | Approved | MORRIS JACKSON |
| Drywall Nailing | 6/28/2023 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 6/28/2023 | Not Ready for Inspection | SEAN HAUPT |
| Final | 3/8/2024 | Corrections Issued | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 3/8/2024 | SGSOV Not Ready | JOHN KIDWELL |
| Smoke Detectors | 3/8/2024 | Approved | JOHN KIDWELL |
| Final | 5/23/2024 | Permit Finaled | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 5/23/2024 | SGSOV Approved | JOHN KIDWELL |