2112-2112 1/2 E 2ND ST 90033

Certificate Information: 2112-2112 1/2 E 2ND ST 90033

Application / Permit
22016-10000-33456
Plan Check / Job No.
B22LA22304
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
EPLAN REMODELING OF 2 UNITS REMOVE NON BEARING WALLS REMODELING FOR KITCHEN 2 BATHROOMS REMODEL TO INCLUDE REWIRE REPIPE FOR WHOLE UNITS CHANGE OT FOR WINDOWS THROW OUT THE UNITS 2112 AND 2112 1/2 E 2ND ST
Permit Issued
Issued on 12/2/2022
Issuing Office
Current Status
Permit Finaled on 9/18/2023

Permit Application Status History

Submitted 11/3/2022 APPLICANT
Assigned to Plan Check Engineer 11/10/2022 SAMUEL GONZALEZ
Corrections Issued 11/14/2022 ZAW HAN
Plan Check Approved 11/30/2022 SAMUEL GONZALEZ
Issued 12/2/2022 APPLICANT
Permit Finaled 8/29/2023 JULIAN CAPUCETTI
CofO in Progress 8/30/2023 JULIAN CAPUCETTI
No Progress 9/18/2023 ERNESTO CORRAL

Permit Application Clearance Information

Tenant Habitability Plan Cleared 11/22/2022 MICHAEL SOTO

Contact Information

Contractor Owner-Builder       ,
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Rough 1/19/2023 Approved RAFAEL CORTES
Wood Frame 1/19/2023 Not Ready for Inspection RAFAEL CORTES
Pre-Inspection 1/25/2023 Partial Approval RAMAZANALI ALMASI
Drywall Nailing 3/21/2023 Approved JULIAN CAPUCETTI
Interior/Exterior Lathing 4/24/2023 Approved JULIAN CAPUCETTI
Interior/Exterior Lathing 5/8/2023 Approved JULIAN CAPUCETTI
Final 8/22/2023 Corrections Issued JULIAN CAPUCETTI
SGSOV-Seismic Gas S/O Valve 8/22/2023 SGSOV Not Ready JULIAN CAPUCETTI
Smoke Detectors 8/22/2023 Approved JULIAN CAPUCETTI
Wood Frame 8/22/2023 Approved JULIAN CAPUCETTI
Final 8/25/2023 Corrections Issued JULIAN CAPUCETTI
SGSOV-Seismic Gas S/O Valve 8/25/2023 SGSOV Not Ready JULIAN CAPUCETTI
Final 8/29/2023 Permit Finaled JULIAN CAPUCETTI
SGSOV-Seismic Gas S/O Valve 8/29/2023 SGSOV Approved JULIAN CAPUCETTI