3430 S POTOMAC AVE 90016

Certificate Information: 3430 S POTOMAC AVE 90016

Application / Permit
22016-10000-33374
Plan Check / Job No.
B22LA22226
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO AN A.D.U. PER GCS 65852.2(e)(1)(A) PER ENGINEERED DESIGN
Permit Issued
Issued on 2/2/2023
Issuing Office
Current Status
CofO Issued on 7/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/2/2022 APPLICANT
Assigned to Plan Check Engineer 11/9/2022 LUKE GONZALES
Corrections Issued 11/12/2022 LUKE GONZALES
Building Plans Picked Up 11/16/2022 APPLICANT
Applicant returned to address corrections 1/27/2023 LAWRENCE QUIRANTE
Plan Check Approved 1/31/2023 DANIEL SMILEY
Issued 2/2/2023 APPLICANT
CofO in Progress 7/7/2023 CALEB MEISTER
Permit Finaled 7/16/2023 DEROLD HAUFF
CofO Issued 7/16/2023 DEROLD HAUFF
Permit Finaled 7/16/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/8/2022 STEVE MELGAR
Sewer availability Cleared 12/8/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 12/14/2022 STEVE MELGAR
Flood clearance Cleared 1/26/2023 BRYAN GATHUKA

Contact Information

Architect Nguyen,, Timothy; Lic. No.: C35111 20 SALTAIRE      LAGUNA NIGUEL, CA 92677
Contractor Suplex Llc; Lic. No.: 1075281-B 846 SOUTH BROADWAY #301      LOS ANGELES, CA 90014
Engineer Baich,, Brendon Chad; Lic. No.: C83347 PO BOX 8840      POMONA, CA 91701

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/7/2023 Corrections Issued CALEB MEISTER
ELECTRICAL-Rough 2/9/2023 Corrections Issued CALEB MEISTER
PLUMBING-Rough 2/9/2023 Corrections Issued CALEB MEISTER
BUILDING-Rough-Frame 2/16/2023 Not Ready for Inspection CALEB MEISTER
ELECTRICAL-Rough 2/16/2023 Not Ready for Inspection CALEB MEISTER
Footing/Foundation/Slab 2/16/2023 Corrections Issued CALEB MEISTER
HVAC-Rough 2/16/2023 Not Ready for Inspection CALEB MEISTER
PLUMBING-Rough 2/16/2023 Not Ready for Inspection CALEB MEISTER
BUILDING-Rough-Frame 3/6/2023 Not Ready for Inspection CALEB MEISTER
PLUMBING-Rough 3/6/2023 Not Ready for Inspection CALEB MEISTER
Pre-Inspection 3/6/2023 Approved CALEB MEISTER
Sewer 3/6/2023 Not Ready for Inspection CALEB MEISTER
BUILDING-Rough-Frame 3/15/2023 Not Ready for Inspection CALEB MEISTER
PLUMBING-Rough 3/15/2023 Not Ready for Inspection CALEB MEISTER
BUILDING-Rough-Frame 3/20/2023 Approved CALEB MEISTER
ELECTRICAL-Rough 3/20/2023 Approved CALEB MEISTER
HVAC-Rough 3/20/2023 Approved CALEB MEISTER
Insulation 3/20/2023 Corrections Issued CALEB MEISTER
PLUMBING-Rough 3/20/2023 Approved CALEB MEISTER
Sewer 3/20/2023 Not Ready for Inspection CALEB MEISTER
Drywall Nailing 3/24/2023 Approved CALEB MEISTER
Sewer 3/24/2023 Not Ready for Inspection CALEB MEISTER
Sewer 3/31/2023 Approved CALEB MEISTER
Final 5/12/2023 Not Ready for Inspection CALEB MEISTER
Green Building Final 5/12/2023 Not Ready for Inspection CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 5/12/2023 SGSOV Not Ready CALEB MEISTER
Smoke Detectors 5/12/2023 Approved CALEB MEISTER
Final 5/19/2023 Not Ready for Inspection CALEB MEISTER
Green Building Final 5/19/2023 Approved CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 5/19/2023 SGSOV Approved CALEB MEISTER
ELECTRICAL-Final 7/6/2023 Approved CALEB MEISTER
Final 7/6/2023 OK to Issue CofO CALEB MEISTER
HVAC-Final 7/6/2023 Approved CALEB MEISTER
PLUMBING-Final 7/6/2023 Approved CALEB MEISTER