642 3/4 N LA JOLLA AVE 90048

Certificate Information: 642 3/4 N LA JOLLA AVE 90048

Application / Permit
22016-10000-33310
Plan Check / Job No.
B22LA22190
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert detached 18 x 20 garage to ADU PER CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g) **SEE COMMENTS**
Permit Issued
Issued on 7/25/2023
Issuing Office
San Pedro
Current Status
CofO Issued on 10/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2022 APPLICANT
Assigned to Plan Check Engineer 11/8/2022 ADAM HEGAZI
Corrections Issued 11/9/2022 ADAM HEGAZI
Applicant returned to address corrections 11/28/2022 JOSEPH RAFOLS
Plan Check Approved 7/25/2023 LAWRENCE QUIRANTE
Issued 7/25/2023 APPLICANT
CofO in Progress 10/1/2024 JOAQUIN GREENOUGH
Permit Finaled 10/16/2024 RUBEN SALAS
Permit Finaled 10/16/2024 RUBEN SALAS
CofO Issued 10/16/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/22/2023 CINDY QI
Sewer availability Cleared 2/22/2023 CINDY QI
Eng Process Fee Ord 176,300 Cleared 3/1/2023 CINDY QI
Tenant Habitability Plan Cleared 3/8/2023 MICHAEL SOTO
Construction near power lines Cleared 7/5/2023 RIDWAN HARDY
Construction within easement Cleared 7/5/2023 RIDWAN HARDY

Contact Information

Architect Ezzati,, Bahman; Lic. No.: C34210 P O BOX 55401      SHERMAN OAKS, CA 91413
Contractor Neighborhood Home; Lic. No.: 638351-B 5410 BAYRIDGE      RANCHO PALOS VERDES, CA 90275

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/18/2023 Conditional Approval LILIANA PORTILLO
Footing/Foundation/Slab 9/18/2023 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 9/18/2023 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 9/26/2023 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 4/8/2024 Corrections Issued AMIR NAZARIAN
PLUMBING-Rough 4/8/2024 Approved AMIR NAZARIAN
ELECTRICAL-Rough 4/10/2024 Conditional Approval AMIR NAZARIAN
ELECTRICAL-Rough 4/16/2024 Approved AMIR NAZARIAN
HVAC-Rough 4/16/2024 Approved AMIR NAZARIAN
BUILDING-Rough-Frame 9/5/2024 Approved JOSE MACIAS
Final 9/5/2024 Corrections Issued JOSE MACIAS
Green Building Final 9/5/2024 Approved JOSE MACIAS
Green Building Rough 9/5/2024 Approved JOSE MACIAS
METHANE-Final 9/5/2024 Approved JOSE MACIAS
METHANE-Rough 9/5/2024 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 9/5/2024 SGSOV Approved JOSE MACIAS
Smoke Detectors 9/5/2024 Approved JOSE MACIAS
Final 9/23/2024 Conditional Approval JOSE MACIAS
ELECTRICAL-Final 10/2/2024 Approved JOAQUIN GREENOUGH
Final 10/2/2024 OK to Issue CofO JOAQUIN GREENOUGH