2117-2117 1/4 W AARON ST 90026
Certificate Information: 2117-2117 1/4 W AARON ST 90026
- Application / Permit
- 22016-10000-33279
- Plan Check / Job No.
- B22LA22162
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Partial interior remodeling of existing single family residence, conversion of 792 sf of existing single family residence into an Accessory dwelling unit PER LAMC 12.22 A.33(c) and (e) ( only one ADU allowed per lot)
- Permit Issued
- Issued on 1/23/2023
- Issuing Office
- Current Status
- CofO Issued on 8/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 11/8/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 12/2/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 12/7/2022 | MOHAMMAD ESMAILI |
| Issued | 1/23/2023 | APPLICANT |
| CofO in Progress | 8/16/2023 | THOMAS LOGRASSO |
| Permit Finaled | 8/23/2023 | DEROLD HAUFF |
| CofO Issued | 8/23/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 11/16/2022 | MICHAEL SOTO |
| Sewer availability | Cleared | 11/17/2022 | CHRISTOPHER ROCHA |
| Address approval | Cleared | 11/18/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 11/30/2022 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/30/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Rough | 1/30/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Wood Frame | 1/30/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 3/15/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Wood Frame | 3/15/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 3/17/2023 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 3/17/2023 | Corrections Issued | FREDDIE RIVERA |
| MERV13>=Rough | 3/17/2023 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 3/17/2023 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 3/23/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 3/23/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 3/31/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 3/31/2023 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 3/31/2023 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 3/31/2023 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 5/2/2023 | Corrections Issued | THOMAS LOGRASSO |
| Insulation | 5/2/2023 | Conditional Approval | THOMAS LOGRASSO |
| Drywall Nailing | 5/11/2023 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 5/16/2023 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 5/16/2023 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 7/18/2023 | Approved | THOMAS LOGRASSO |
| Final | 8/7/2023 | Corrections Issued | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 8/7/2023 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 8/7/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 8/15/2023 | OK to Issue CofO | THOMAS LOGRASSO |
| Smoke Detectors | 8/15/2023 | Approved | THOMAS LOGRASSO |