847 S SHERBOURNE DR 1-13 90035

Certificate Information: 847 S SHERBOURNE DR 1-13 90035

Application / Permit
22016-10000-33277
Plan Check / Job No.
B22LA22160
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
INTERIOR REMODEL OF EXISITING (12) UNITS IN EXISITING MULTI-FAMILY RESIDENTIAL BUILDING INCLUDING REVISED LAYOUTS OF INTERIOR UNIT WALLS, NEW WINDOWS AND DOORS. EXTERIOR REMODEL OF EASTFACADE ON SHERBROUNE DRIVE. NEW INTERIOR FINISHES THROUGHOUT INCLUDING FLOORING, CABINETS AND FIXTURES. SCOPE ALSO INCLUDES CONVERSION OF (E) ELEC, MECH, AND LAUNDRY ROOM IN GROUND FLOOR INTO A STUDIO ACCESSORY DWELLING UNIT PER GCS 65852.2(E) (1) (C)
Permit Issued
Issued on 5/12/2023
Issuing Office
Valley
Current Status
CofO Issued on 10/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2022 APPLICANT
Assigned to Plan Check Engineer 11/3/2022 MARCELA FRANQUEZ
Corrections Issued 11/18/2022 MARCELA FRANQUEZ
Quality Review Completed 11/28/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 12/1/2022 APPLICANT
Applicant returned to address corrections 12/19/2022 MARCELA FRANQUEZ
Applicant returned to address corrections 1/20/2023 MARCELA FRANQUEZ
Green Plans Picked Up 1/25/2023 APPLICANT
Plan Check Approved 2/13/2023 MARCELA FRANQUEZ
Issued 5/12/2023 APPLICANT
CofO in Progress 10/28/2024 FARHAD DADBIN
Permit Finaled 10/31/2024 DAVID TSAU
CofO Issued 10/31/2024 DAVID TSAU
Permit Finaled 10/31/2024 DAVID TSAU

Permit Application Clearance Information

"Q" conditions Cleared 12/14/2022 DALIA MOKAYED
CPC Cleared 12/14/2022 DALIA MOKAYED
ZA Case Cleared 12/14/2022 DALIA MOKAYED
Address approval Cleared 12/15/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 12/16/2022 JEANIE LAM
Sewer availability Cleared 12/16/2022 JEANIE LAM
Green Code Cleared 2/8/2023 AARON COSTA

Contact Information

Contractor M Librush Construction Inc; Lic. No.: 933238-B 541 SOUTH SPRING ST STE 213      LOS ANGELES, CA 90013

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 7/18/2023 Partial Inspection FARHAD DADBIN
Pre-Inspection 8/14/2023 Approved FARHAD DADBIN
Deputy Drilled-In Anchors 8/25/2023 Conditional Approval FARHAD DADBIN
Footing/Foundation/Slab 8/25/2023 Partial Approval FARHAD DADBIN
Pre-Inspection 9/1/2023 Approved FARHAD DADBIN
Deputy Wood Construction 12/26/2023 Conditional Approval FARHAD DADBIN
Wood Frame 1/9/2024 Conditional Approval FARHAD DADBIN
Drywall Nailing 1/31/2024 Not Ready for Inspection FARHAD DADBIN
Insulation 1/31/2024 Approved FARHAD DADBIN
Interior/Exterior Lathing 1/31/2024 Approved FARHAD DADBIN
Wood Frame 1/31/2024 Partial Approval FARHAD DADBIN
Special/Order Compliance 2/8/2024 Approved FARHAD DADBIN
Drywall Nailing 2/14/2024 Partial Approval FARHAD DADBIN
Drywall Nailing 2/27/2024 Partial Approval FARHAD DADBIN
Insulation 3/27/2024 Conditional Approval FARHAD DADBIN
Drywall Nailing 4/1/2024 Approved FARHAD DADBIN
Interior/Exterior Lathing 4/4/2024 Conditional Approval FARHAD DADBIN
Wood Frame 5/17/2024 Partial Approval FARHAD DADBIN
Footing/Foundation/Slab 7/3/2024 Partial Approval FARHAD DADBIN
Deputy Reinf. Concrete 7/10/2024 Conditional Approval FARHAD DADBIN
Deputy Drilled-In Anchors 7/17/2024 Conditional Approval FARHAD DADBIN
Footing/Foundation/Slab 7/22/2024 Partial Approval FARHAD DADBIN
Structural Steel Frame 7/22/2024 Approved FARHAD DADBIN
Deputy Reinf. Concrete 8/5/2024 Conditional Approval FARHAD DADBIN
Final 10/23/2024 Partial Approval FARHAD DADBIN
Green Building Final 10/23/2024 Approved FARHAD DADBIN
METHANE-Final 10/23/2024 Approved FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 10/23/2024 SGSOV Approved FARHAD DADBIN
Smoke Detectors 10/23/2024 Approved FARHAD DADBIN
Final 10/25/2024 Not Ready for Inspection FARHAD DADBIN
Final 10/28/2024 OK to Issue CofO FARHAD DADBIN