558 S WESTERN AVE 90020

Certificate Information: 558 S WESTERN AVE 90020

Application / Permit
22016-10000-33209
Plan Check / Job No.
B22LA22102
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
CHANGE THE USE OF (E) RETAIL SPACE TO RESTAURANT IN EXISTING COMMERCIAL BUILDING. HOURS OF OPERATION FROM 7AM TO 11PM.
Permit Issued
Issued on 6/28/2023
Issuing Office
Metro
Current Status
CofO Issued on 11/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2022 APPLICANT
Assigned to Plan Check Engineer 11/9/2022 AUNG SOE
Corrections Issued 11/14/2022 AUNG SOE
Building Plans Picked Up 11/18/2022 APPLICANT
Plan Check Approved 2/21/2023 RICARDO RAMIREZ
Issued 6/28/2023 APPLICANT
CofO in Progress 11/25/2025 ALFREDO LOPEZ
CofO in Progress 11/25/2025 JAMES POWERS
CofO in Progress 11/25/2025 ALFREDO LOPEZ
Permit Finaled 11/25/2025 ERNESTO CORRAL
CofO Issued 11/25/2025 ERNESTO CORRAL
Permit Finaled 11/25/2025 ERNESTO CORRAL

Permit Application Clearance Information

Comm Cor/Mini-Mall Cleared 11/22/2022 MAXFIELD VERMY
Historic Resource Verification Cleared 11/22/2022 MAX LODER
Eng Process Fee Ord 176,300 Cleared 12/2/2022 CHRISTOPHER ROCHA
ZA Case Cleared 12/20/2022 OMAR GALICIA
ZA Case Cleared 12/20/2022 OMAR GALICIA
Food establishment approval Cleared 12/21/2022 LACDHS APPROVED
Redevelopment Project Area Cleared 12/22/2022 DAVID URITA
Food Service Establishment Cleared 1/25/2023 KENNETH BROWNE
Sewer availability Cleared 2/1/2023 CHRISTOPHER ROCHA

Contact Information

Architect Kelly,, George William; Lic. No.: C26144 1107 S WINDSOR BLVD      LOS ANGELES, CA 90019
Contractor Jungsco Inc; Lic. No.: 951264-B 1885 COMMONWEALTH AVE_UNIT B      FULLERTON, CA 92833
Engineer Tan,, Charles; Lic. No.: S4758 3161 DRIGGS AVENUE      ROSEMEAD, CA 91770

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/29/2023 Conditional Approval TIMOTHY POWELL
Footing/Foundation/Slab 8/29/2023 Partial Approval TIMOTHY POWELL
Pre-Inspection 8/29/2023 Not Ready for Inspection TIMOTHY POWELL
Light Gage Steel Frame 9/13/2023 Not Ready for Inspection TIMOTHY POWELL
Pre-Inspection 9/13/2023 Approved TIMOTHY POWELL
Pre-Inspection 9/20/2023 Not Ready for Inspection ALFREDO LOPEZ
Wood Frame 9/20/2023 Not Ready for Inspection ALFREDO LOPEZ
Light Gage Steel Frame 10/4/2023 Not Ready for Inspection TIMOTHY POWELL
Pre-Inspection 10/4/2023 Not Ready for Inspection TIMOTHY POWELL
Wood Frame 10/4/2023 Not Ready for Inspection TIMOTHY POWELL
Wood Frame 10/17/2023 Conditional Approval DARRYL ARNOLD
Wood Frame 10/19/2023 Not Ready for Inspection ALFREDO LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/23/2023 Partial Approval ALFREDO LOPEZ
Light Gage Steel Frame 11/1/2023 Partial Approval KATY RAMIREZ
Insulation 11/9/2023 Approved MARTIN TAVITIAN
Drywall Nailing 11/29/2023 Partial Approval LUIS CCAMACHO
Drywall Nailing 1/17/2024 Partial Approval MARTIN TAVITIAN
Light Gage Steel Frame 1/18/2024 Partial Approval MARTIN TAVITIAN
Pre-Inspection 1/18/2024 Partial Approval MARTIN TAVITIAN
Light Gage Steel Frame 1/29/2024 Not Ready for Inspection JEROME BLACKWOOD
Footing/Foundation/Slab 2/29/2024 Not Ready for Inspection RAFAEL CORTES
Deputy Reinf. Concrete 3/5/2024 Conditional Approval RAFAEL CORTES
Reinforced Concrete Frame 3/5/2024 Partial Approval RAFAEL CORTES
Drywall Nailing 3/27/2024 Corrections Issued RAFAEL CORTES
T-Bar Ceiling 4/24/2024 Not Ready for Inspection TIMOTHY POWELL
T-Bar Ceiling 8/30/2024 Not Ready for Inspection TIMOTHY POWELL
Final 11/21/2025 OK to Issue CofO ALFREDO LOPEZ
Green Building Final 11/21/2025 Approved ALFREDO LOPEZ
Green Building Rough 11/21/2025 Approved ALFREDO LOPEZ
Reinforced Masonry Frame 11/21/2025 Approved ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 11/21/2025 SGSOV Approved ALFREDO LOPEZ
Smoke Detectors 11/21/2025 Approved ALFREDO LOPEZ