111 W AVENUE 31 90031

Certificate Information: 111 W AVENUE 31 90031

Application / Permit
22016-10000-33185
Plan Check / Job No.
B22LA22085
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT AND EXPAND THE EXISITNG DETACHED GARAGE INTO A ACCESSORY DWELLING UNIT PER CODE 65852.2(e)(1)(A). NEW ATTACHED REC ROOM TO ADU.
Permit Issued
Issued on 3/23/2023
Issuing Office
Current Status
Issued on 3/23/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/2/2022 APPLICANT
Assigned to Plan Check Engineer 11/10/2022 JOE VO
Plan Check Approved 3/21/2023 JOE VO
Issued 3/23/2023 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 12/17/2022 GILBERT URREA
Address approval Cleared 3/10/2023 TREVOR QUAN
Low Impact Development Cleared 3/10/2023 MARTIN FRAGOSO
Eng Process Fee Ord 176,300 Cleared 3/13/2023 AMAAN MALIK
Roof/Waste drainage to street Cleared 3/13/2023 AMAAN MALIK
Sewer availability Cleared 3/13/2023 AMAAN MALIK
Hold Cleared 4/18/2023 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/24/2023 Partial Inspection ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 5/5/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Pre-Inspection 5/5/2023 Partial Inspection ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 6/13/2023 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 6/14/2023 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 8/30/2023 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 8/30/2023 Partial Approval OSVALDO PARAMO
Deputy Other (see comments) 9/19/2023 Conditional Approval OSVALDO PARAMO
PLUMBING-Rough 10/11/2023 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 10/19/2023 Approved OSVALDO PARAMO
Underground Mechanical 10/19/2023 Partial Approval OSVALDO PARAMO
ELECTRICAL-Rough 1/10/2024 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 1/10/2024 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Rough 3/13/2024 Approved LILIANA PORTILLO
PLUMBING-Rough 3/13/2024 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 4/10/2024 Partial Approval OSVALDO PARAMO
Deputy Wood Construction 5/1/2024 Conditional Approval OSVALDO PARAMO
BUILDING-Rough-Frame 7/2/2024 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 7/2/2024 Approved OSVALDO PARAMO
Green Building Rough 7/2/2024 Not Ready for Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 7/11/2024 Approved OSVALDO PARAMO
Green Building Rough 7/11/2024 Approved OSVALDO PARAMO
Insulation 7/18/2024 Approved OSVALDO PARAMO
Wood Frame 7/18/2024 Approved OSVALDO PARAMO
Drywall Nailing 7/25/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 8/30/2024 Approved LUIS CASTRO
ELECTRICAL-Final 11/18/2024 Corrections Issued ALIZAH MAYAGOITIA
HVAC-Final 11/18/2024 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Final 11/18/2024 Corrections Issued ALIZAH MAYAGOITIA
Final 12/6/2024 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 12/6/2024 Approved ALIZAH MAYAGOITIA
Green Building Final 12/6/2024 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 12/6/2024 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 12/6/2024 Approved ALIZAH MAYAGOITIA
Final 12/31/2024 Not Ready for Inspection ALIZAH MAYAGOITIA