2020 N HILLHURST AVE 90027

Certificate Information: 2020 N HILLHURST AVE 90027

Application / Permit
22016-10000-33058
Plan Check / Job No.
B22LA21990
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Soft story retrofit of a 2 story apartment building. Work to utilize one Special Steel cantilevered column.
Permit Issued
Issued on 5/15/2023
Issuing Office
Current Status
CofC Issued on 10/10/2023

Permit Application Status History

Submitted 10/31/2022 APPLICANT
Assigned to Plan Check Engineer 11/17/2022 HANS SANTIAGO
Corrections Issued 11/21/2022 HANS SANTIAGO
Quality Review Completed 11/21/2022 LIPING TENG
Plan Check Approved 12/19/2022 ANDREW SANTIAGO
Issued 5/15/2023 APPLICANT
OK for CofC 10/6/2023 VAHE KELEDJIAN
CofC Issued 10/10/2023 WINSTON DUNNING

Permit Application Clearance Information

Tenant Habitability Plan Cleared 4/25/2023 RICARDO BOHORQUEZ

Contact Information

Architect Miller,, Michael; Lic. No.: NA26956       ,
Contractor K N D Construction Inc; Lic. No.: 969756-B       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/21/2023 Corrections Issued DARRYL ARNOLD
Deputy Drilled-In Anchors 7/6/2023 Conditional Approval DARRYL ARNOLD
Deputy Steel/Welding 7/6/2023 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 7/6/2023 Conditional Approval DARRYL ARNOLD
Structural Steel Frame 7/6/2023 Not Ready for Inspection DARRYL ARNOLD
Wood Frame 7/6/2023 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 7/14/2023 Conditional Approval DARRYL ARNOLD
Final 10/6/2023 OK for CofC VAHE KELEDJIAN
SGSOV-Seismic Gas S/O Valve 10/6/2023 SGSOV Approved VAHE KELEDJIAN
Smoke Detectors 10/6/2023 Approved VAHE KELEDJIAN