854-854 1/2 E 106TH ST 90002

Certificate Information: 854-854 1/2 E 106TH ST 90002

Application / Permit
22016-10000-32897
Plan Check / Job No.
B22LA21873
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Add one story ADU to rear of (E) 1-story SFD per LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 11/18/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2022 APPLICANT
Assigned to Plan Check Engineer 11/8/2022 DANIEL SMILEY
Corrections Issued 11/8/2022 DANIEL SMILEY
Building Plans Picked Up 11/10/2022 APPLICANT
Plan Check Approved 11/16/2022 SAMUEL GONZALEZ
Issued 11/18/2022 APPLICANT
CofO in Progress 4/5/2024 BEN MOLSTAD
CofO Issued 4/5/2024 ANSON MAGLASANG
Permit Finaled 4/5/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 11/9/2022 STEVE MELGAR
Roof/Waste drainage to street Cleared 11/9/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 11/16/2022 STEVE MELGAR
Sewer availability Cleared 11/16/2022 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/10/2023 Approved JOHN KLARIN
BUILDING-Rough-Frame 3/9/2023 Corrections Issued JOHN KLARIN
PLUMBING-Rough 3/9/2023 Corrections Issued JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 3/13/2023 Approved JAMES CHAVEZ
Underground Mechanical 3/13/2023 Approved JAMES CHAVEZ
Insulation 3/24/2023 Approved JOHN KLARIN
BUILDING-Rough-Frame 8/9/2023 Corrections Issued JOHN KLARIN
Green Building Rough 8/9/2023 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 8/14/2023 Partial Approval JOHN KLARIN
ELECTRICAL-Rough 8/14/2023 Approved JOHN KLARIN
Green Building Rough 8/14/2023 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 8/14/2023 Approved JOHN KLARIN
Insulation 8/24/2023 Corrections Issued JAMES CHAVEZ
Interior/Exterior Lathing 8/24/2023 Not Ready for Inspection JAMES CHAVEZ
Insulation 9/13/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 9/20/2023 Approved JOHN KLARIN
BUILDING-Rough-Frame 1/29/2024 Approved JAMES CHAVEZ
Drywall Nailing 1/29/2024 Approved JAMES CHAVEZ
Final 1/29/2024 Corrections Issued JAMES CHAVEZ
Green Building Final 1/29/2024 Not Ready for Inspection JAMES CHAVEZ
Green Building Rough 1/29/2024 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 1/29/2024 SGSOV Not Ready JAMES CHAVEZ
Smoke Detectors 1/29/2024 Not Ready for Inspection JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 2/7/2024 SGSOV Not Ready JAMES CHAVEZ
Final 2/23/2024 Corrections Issued BEN MOLSTAD
Green Building Final 2/23/2024 Not Ready for Inspection BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 2/23/2024 SGSOV Not Ready BEN MOLSTAD
Smoke Detectors 2/23/2024 Corrections Issued BEN MOLSTAD
Final 2/29/2024 Corrections Issued BEN MOLSTAD
Green Building Final 2/29/2024 Approved BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 2/29/2024 SGSOV Approved BEN MOLSTAD
Smoke Detectors 2/29/2024 Approved BEN MOLSTAD
ELECTRICAL-Final 4/3/2024 Approved BEN MOLSTAD
Final 4/3/2024 OK to Issue CofO BEN MOLSTAD