8500 W BEVERLY BLVD 767 90048

Certificate Information: 8500 W BEVERLY BLVD 767 90048

Application / Permit
22016-10000-32858
Plan Check / Job No.
B22LA21851
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
EPLAN: tenant improvements to an existing store located on level 7 of the beverly center mall. (all interior work) work includes (n)non-structural partitions, (n) ceiling, (n)storefront & associated structural framing for metal soffits, (n) casework, (n) ceiling-lighting and (n) architectural finishes. separate permits for mep
Permit Issued
Issued on 12/21/2022
Issuing Office
Current Status
Permit Finaled on 2/9/2024

Permit Application Status History

Submitted 10/28/2022 APPLICANT
Assigned to Plan Check Engineer 11/4/2022 SAMUEL GONZALEZ
Corrections Issued 11/7/2022 AUNG SOE
Plan Check Approved 11/30/2022 SAMUEL GONZALEZ
Issued 12/21/2022 APPLICANT
Permit Finaled 1/11/2024 ALFREDO LOPEZ

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Susanna, Chan; Lic. No.: C38399       ,
Contractor Dickinson Cameron Construction Company Inc; Lic. No.: 690239-B       ,
Engineer Chavda,, Alpesh Kishorsinh; Lic. No.: C73666 5133 HILLIARD GREEN DR      HILLIARD, OH 43026
Engineer Chavda,, Alpesh Kishorsinh; Lic. No.: NA73666       ,

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/6/2023 Approved ALFREDO LOPEZ
Light Gage Steel Frame 2/13/2023 Not Ready for Inspection JEROME BLACKWOOD
T-Bar Ceiling 2/13/2023 Not Ready for Inspection JEROME BLACKWOOD
Light Gage Steel Frame 2/22/2023 Approved MARTIN TAVITIAN
Drywall Nailing 2/23/2023 Partial Approval JEROME BLACKWOOD
Light Gage Steel Frame 2/23/2023 Partial Approval JEROME BLACKWOOD
Structural Steel Frame 2/23/2023 Partial Approval JEROME BLACKWOOD
T-Bar Ceiling 2/23/2023 Partial Approval JEROME BLACKWOOD
Pre-Inspection 4/14/2023 Approved ALFREDO LOPEZ
Smoke Detectors 4/14/2023 Not Ready for Inspection ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 4/25/2023 SGSOV Not Ready ALFREDO LOPEZ
Smoke Detectors 4/25/2023 Not Ready for Inspection ALFREDO LOPEZ
Final 5/2/2023 Not Ready for Inspection JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 5/2/2023 SGSOV Not Required JEROME BLACKWOOD
Smoke Detectors 5/2/2023 Approved JEROME BLACKWOOD
Final 1/11/2024 Permit Finaled ALFREDO LOPEZ