7800 WORLD WAY WEST 90045
Certificate Information: 7800 WORLD WAY WEST 90045
- Application / Permit
- 22016-10000-32745
- Plan Check / Job No.
- B22LA21749
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (3) Aircraft Hanger
- Work Description
- **ePlan Ref# 73578**LAX** T.I. for existing LAX hangar (QANTAS), including: At ground level, demo existing break/training room to contruct & expand existing Work Control Center on the Ground Level. New bollards and housekeeping pad. At mezzanine level, change of use from S-1 occupancy work benches and groom cell into A-2 Occupancy Break room and Lounge and reconfiguration of the Mens & Womens Restrooms / Locker rooms. At second level, installation of a new window on the Hangar side of the Offices. T.I. work includes new nonbearing partitions and suspended ceiling.
- Permit Issued
- Issued on 6/23/2023
- Issuing Office
- Current Status
- CofO Issued on 3/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2022 | CATHERINE CHEN |
| Corrections Issued | 11/22/2022 | CATHERINE CHEN |
| Quality Review Completed | 11/22/2022 | LIPING TENG |
| Applicant returned to address corrections | 12/20/2022 | CATHERINE CHEN |
| Applicant returned to address corrections | 1/25/2023 | CATHERINE CHEN |
| Applicant returned to address corrections | 1/26/2023 | CATHERINE CHEN |
| Applicant returned to address corrections | 1/27/2023 | CATHERINE CHEN |
| Applicant returned to address corrections | 2/2/2023 | CATHERINE CHEN |
| Applicant returned to address corrections | 3/1/2023 | CATHERINE CHEN |
| Applicant returned to address corrections | 3/31/2023 | CATHERINE CHEN |
| Plan Check Approved | 5/12/2023 | CATHERINE CHEN |
| Issued | 6/23/2023 | APPLICANT |
| CofO in Progress | 3/20/2024 | NICK LAROCCA |
| Permit Finaled | 3/20/2024 | NICK LAROCCA |
| CofO Issued | 3/20/2024 | NICK LAROCCA |
| Permit Finaled | 3/20/2024 | NICK LAROCCA |
Permit Application Clearance Information
| Sewer availability | Cleared | 12/22/2022 | HISASHI KOBAYAKAWA |
| City owned building/parcel | Cleared | 1/3/2023 | CATHERINE CHEN |
| Tract Map conditions | Cleared | 1/3/2023 | LOUIS ORTEGA |
| Tract Map conditions | Cleared | 1/3/2023 | LOUIS ORTEGA |
| Eng Process Fee Ord 176,300 | Cleared | 2/9/2023 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 3/2/2023 | FREDDY GARCIA |
| Green Code | Cleared | 3/9/2023 | AARON COSTA |
| Project Permit | Cleared | 3/22/2023 | CATHERINE CHEN |
| DAS Clearance | Cleared | 3/28/2023 | Lily Teng |
| Airport buildings | Cleared | 3/31/2023 | ANDREW KO |
Contact Information
| Architect | , ; Lic. No.: C34755 | 3530 CLAREMORE AVENUE LONG BEACH, CA 90808 |
| Contractor | Technion Contractors T C I Inc; Lic. No.: 836664-B | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/28/2023 | No Access for Inspection | ALAN NOVAK |
| Pre-Inspection | 7/10/2023 | Approved | NICK LAROCCA |
| Light Gage Steel Frame | 7/18/2023 | Partial Approval | ALAN NOVAK |
| Light Gage Steel Frame | 8/1/2023 | Partial Approval | NICK LAROCCA |
| Drywall Nailing | 8/8/2023 | Partial Approval | NICK LAROCCA |
| Light Gage Steel Frame | 8/24/2023 | Not Ready for Inspection | NICK LAROCCA |
| Light Gage Steel Frame | 9/1/2023 | Partial Approval | NICK LAROCCA |
| T-Bar Ceiling | 9/11/2023 | Corrections Issued | NICK LAROCCA |
| Drywall Nailing | 9/14/2023 | Partial Approval | NICK LAROCCA |
| T-Bar Ceiling | 10/16/2023 | Partial Approval | NICK LAROCCA |
| Light Gage Steel Frame | 11/17/2023 | Approved | NICK LAROCCA |
| Drywall Nailing | 11/22/2023 | Approved | NICK LAROCCA |
| T-Bar Ceiling | 1/12/2024 | Partial Approval | ALAN NOVAK |
| Final | 2/21/2024 | OK to Issue CofO | NICK LAROCCA |
| Green Building Final | 2/21/2024 | Approved | NICK LAROCCA |
| Green Building Rough | 2/21/2024 | Approved | NICK LAROCCA |
| METHANE-Final | 2/21/2024 | Approved | NICK LAROCCA |
| METHANE-Rough | 2/21/2024 | Approved | NICK LAROCCA |
| Reinforced Masonry Frame | 2/21/2024 | Approved | NICK LAROCCA |
| SGSOV-Seismic Gas S/O Valve | 2/21/2024 | SGSOV Approved | NICK LAROCCA |
| Smoke Detectors | 2/21/2024 | Approved | NICK LAROCCA |