7338 W 90TH ST 90045

Certificate Information: 7338 W 90TH ST 90045

Application / Permit
22016-10000-32700
Plan Check / Job No.
B22LA21722
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN Remodel of (E) 1-story SFD w/ att Garage and Addition of rear covered patio
Permit Issued
Issued on 1/23/2023
Issuing Office
Current Status
CofO Issued on 7/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/27/2022 APPLICANT
Assigned to Plan Check Engineer 11/2/2022 MINA HABILI
Corrections Issued 11/3/2022 MINA HABILI
Applicant returned to address corrections 1/19/2023 JOSEPH RAFOLS
Plan Check Approved 1/23/2023 MINA HABILI
Issued 1/23/2023 APPLICANT
CofO in Progress 7/20/2023 BOBBY KEY
Permit Finaled 7/24/2023 DANIEL ORRANTE
CofO Issued 7/24/2023 DANIEL ORRANTE
Permit Finaled 7/24/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/8/2022 CATHERINE ADROVER
Roof/Waste drainage to street Cleared 12/8/2022 CATHERINE ADROVER
Specific Plan Cleared 12/29/2022 PEDRO AYALA
Grading Pre-Inspection Cleared 1/19/2023 JOSEPH RAFOLS

Contact Information

Contractor Owner-Builder       ,
Engineer Piedra,, Casey Pechae; Lic. No.: S6413 295 W CALIFORNIA BLVD #2      PASADENA, CA 91105

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/9/2023 Conditional Approval BOBBY KEY
Excavation/Setback/Form/Re-Bar 3/13/2023 Approved BOBBY KEY
Footing/Foundation/Slab 3/13/2023 Approved BOBBY KEY
Wood Frame 3/28/2023 Partial Approval BOBBY KEY
ELECTRICAL-Rough 4/12/2023 Approved BOBBY KEY
HVAC-Rough 4/12/2023 Approved BOBBY KEY
PLUMBING-Rough 4/12/2023 Approved BOBBY KEY
BUILDING-Rough-Frame 4/14/2023 Corrections Issued BOBBY KEY
Green Building Rough 4/14/2023 Not Ready for Inspection BOBBY KEY
Interior/Exterior Lathing 4/14/2023 Not Ready for Inspection BOBBY KEY
BUILDING-Rough-Frame 4/19/2023 Approved BOBBY KEY
Green Building Rough 4/19/2023 Approved BOBBY KEY
Interior/Exterior Lathing 4/19/2023 Partial Approval BOBBY KEY
Insulation 4/21/2023 Approved BOBBY KEY
Drywall Nailing 4/27/2023 Approved BOBBY KEY
Smoke Detectors 4/27/2023 Corrections Issued BOBBY KEY
Shower Pan 5/15/2023 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 5/17/2023 Approved BOBBY KEY
Shower Pan 5/17/2023 Approved BOBBY KEY
ELECTRICAL-Final 7/13/2023 Corrections Issued HERBERT GIRON
HVAC-Final 7/13/2023 Approved HERBERT GIRON
PLUMBING-Final 7/13/2023 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 7/13/2023 SGSOV Approved HERBERT GIRON
ELECTRICAL-Final 7/17/2023 Approved BOBBY KEY
Final 7/17/2023 Corrections Issued BOBBY KEY
Gas Test 7/17/2023 Approved BOBBY KEY
Green Building Final 7/17/2023 Approved BOBBY KEY
PLUMBING-Final 7/17/2023 Approved BOBBY KEY
Smoke Detectors 7/17/2023 Approved BOBBY KEY
Final 7/20/2023 OK to Issue CofO BOBBY KEY