7338 W 90TH ST 90045
Certificate Information: 7338 W 90TH ST 90045
- Application / Permit
- 22016-10000-32700
- Plan Check / Job No.
- B22LA21722
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN Remodel of (E) 1-story SFD w/ att Garage and Addition of rear covered patio
- Permit Issued
- Issued on 1/23/2023
- Issuing Office
- Current Status
- CofO Issued on 7/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/2/2022 | MINA HABILI |
| Corrections Issued | 11/3/2022 | MINA HABILI |
| Applicant returned to address corrections | 1/19/2023 | JOSEPH RAFOLS |
| Plan Check Approved | 1/23/2023 | MINA HABILI |
| Issued | 1/23/2023 | APPLICANT |
| CofO in Progress | 7/20/2023 | BOBBY KEY |
| Permit Finaled | 7/24/2023 | DANIEL ORRANTE |
| CofO Issued | 7/24/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/24/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2022 | CATHERINE ADROVER |
| Roof/Waste drainage to street | Cleared | 12/8/2022 | CATHERINE ADROVER |
| Specific Plan | Cleared | 12/29/2022 | PEDRO AYALA |
| Grading Pre-Inspection | Cleared | 1/19/2023 | JOSEPH RAFOLS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Piedra,, Casey Pechae; Lic. No.: S6413 | 295 W CALIFORNIA BLVD #2 PASADENA, CA 91105 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/9/2023 | Conditional Approval | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 3/13/2023 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 3/13/2023 | Approved | BOBBY KEY |
| Wood Frame | 3/28/2023 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 4/12/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 4/12/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 4/12/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 4/14/2023 | Corrections Issued | BOBBY KEY |
| Green Building Rough | 4/14/2023 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 4/14/2023 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 4/19/2023 | Approved | BOBBY KEY |
| Green Building Rough | 4/19/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 4/19/2023 | Partial Approval | BOBBY KEY |
| Insulation | 4/21/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 4/27/2023 | Approved | BOBBY KEY |
| Smoke Detectors | 4/27/2023 | Corrections Issued | BOBBY KEY |
| Shower Pan | 5/15/2023 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 5/17/2023 | Approved | BOBBY KEY |
| Shower Pan | 5/17/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 7/13/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 7/13/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 7/13/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 7/13/2023 | SGSOV Approved | HERBERT GIRON |
| ELECTRICAL-Final | 7/17/2023 | Approved | BOBBY KEY |
| Final | 7/17/2023 | Corrections Issued | BOBBY KEY |
| Gas Test | 7/17/2023 | Approved | BOBBY KEY |
| Green Building Final | 7/17/2023 | Approved | BOBBY KEY |
| PLUMBING-Final | 7/17/2023 | Approved | BOBBY KEY |
| Smoke Detectors | 7/17/2023 | Approved | BOBBY KEY |
| Final | 7/20/2023 | OK to Issue CofO | BOBBY KEY |