5246-5246 1/2 W 8TH ST 90036

Certificate Information: 5246-5246 1/2 W 8TH ST 90036

Application / Permit
22016-10000-32570
Plan Check / Job No.
B22LA21630
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Convert (E) storage/recreation rooms into 2 (N) Detached ADU's per 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g)
Permit Issued
Issued on 11/15/2024
Issuing Office
Current Status
CofO Issued on 11/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/26/2022 APPLICANT
Assigned to Plan Check Engineer 11/1/2022 RICARDO RAMIREZ
Corrections Issued 11/2/2022 RICARDO RAMIREZ
Applicant returned to address corrections 5/8/2023 JOSEPH RAFOLS
Applicant returned to address corrections 11/4/2024 JOSEPH RAFOLS
Plan Check Approved 11/14/2024 JOSEPH RAFOLS
Issued 11/15/2024 APPLICANT
CofO in Progress 11/7/2025 RONNIE MINDANAO
Permit Finaled 11/10/2025 DEROLD HAUFF
CofO Issued 11/10/2025 DEROLD HAUFF
Permit Finaled 11/10/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/7/2023 JEANIE LAM
Sewer availability Cleared 2/7/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 2/8/2023 JEANIE LAM
Construction near power lines Cleared 5/7/2023 PATRICK MAGALLANES

Contact Information

Contractor Embark Adu; Lic. No.: 970997-B       ,
Contractor Esk Construction Inc; Lic. No.: 970997-B       ,

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/5/2024 Corrections Issued RONNIE MINDANAO
Pre-Inspection 12/9/2024 Partial Approval RONNIE MINDANAO
Deputy Drilled-In Anchors 12/18/2024 Conditional Approval RONNIE MINDANAO
Excavation/Setback/Form/Re-Bar 12/20/2024 Approved RONNIE MINDANAO
Footing/Foundation/Slab 1/23/2025 Partial Approval JOAQUIN GREENOUGH
Wood Frame 1/23/2025 Not Ready for Inspection JOAQUIN GREENOUGH
Deputy Drilled-In Anchors 1/27/2025 Conditional Approval RONNIE MINDANAO
Footing/Foundation/Slab 2/10/2025 Approved ENRIQUE MIRELES
Insulation 2/24/2025 Corrections Issued RONNIE MINDANAO
Special/Order Compliance 2/27/2025 Approved RONNIE MINDANAO
Insulation 3/3/2025 Corrections Issued RONNIE MINDANAO
Interior/Exterior Lathing 3/3/2025 Approved RONNIE MINDANAO
Wood Frame 3/3/2025 Approved RONNIE MINDANAO
Drywall Nailing 3/12/2025 Approved RONNIE MINDANAO
Insulation 3/12/2025 Approved RONNIE MINDANAO
Final 6/27/2025 Corrections Issued RONNIE MINDANAO
METHANE-Final 6/27/2025 Approved RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 6/27/2025 SGSOV Not Required RONNIE MINDANAO
Smoke Detectors 6/27/2025 Corrections Issued RONNIE MINDANAO
Final 7/7/2025 Corrections Issued RONNIE MINDANAO
Smoke Detectors 7/7/2025 Approved RONNIE MINDANAO
Final 7/10/2025 Corrections Issued RONNIE MINDANAO
Final 10/30/2025 Partial Approval RONNIE MINDANAO
Final 11/6/2025 OK to Issue CofO RONNIE MINDANAO