1452 S 12TH AVE 90019

Certificate Information: 1452 S 12TH AVE 90019

Application / Permit
22016-10000-32554
Plan Check / Job No.
B22LA21614
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: Convert existing detached garage to ADU per state law. ALL WORK DONE PER WFPP\ ****Code Enforcement Bureau has issued an order. This parcel is eligible for issuance of a 30 day time limit permit (including Building, Electrical, HVAC and Plumbing) with a work description as follows. "COMPLY WITH DEPARTMENT ORDER effective date 07/19/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". All permits shall be for the same time period limitation. If additional assistance is needed, please call Inspector GLEN RAND at (213)252-3957 of GENERAL ENFORCEMENT SOUTH. CEIS Case Number is 963419.****
Permit Issued
Issued on 7/18/2023
Issuing Office
Current Status
CofO Issued on 4/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/26/2022 APPLICANT
Assigned to Plan Check Engineer 11/1/2022 RICARDO RAMIREZ
Corrections Issued 11/2/2022 RICARDO RAMIREZ
Plan Check Approved 2/22/2023 KHUONG TRUONG
Issued 7/18/2023 APPLICANT
CofO in Progress 4/8/2025 WILLIAM MICHALAK
CofO in Progress 4/15/2025 WILLIAM MICHALAK
Permit Finaled 4/18/2025 CLAUDIO MORENO
CofO Issued 4/18/2025 CLAUDIO MORENO
Permit Finaled 4/18/2025 CLAUDIO MORENO

Permit Application Clearance Information

Address approval Cleared 12/7/2022 TREVOR QUAN
Sewer availability Cleared 12/7/2022 TREVOR QUAN
Community Plan Implem. Overlay Cleared 12/8/2022 KYLE WINSTON
ZI Cleared 12/8/2022 KYLE WINSTON
Construction near power lines Cleared 2/9/2023 NADER ISKANDER
Eng Process Fee Ord 176,300 Cleared 2/16/2023 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/10/2023 Approved GLEN RAND
Footing/Foundation/Slab 8/17/2023 Conditional Approval GLEN RAND
Deputy Drilled-In Anchors 9/8/2023 No Access for Inspection WILLIAM MICHALAK
BUILDING-Rough-Frame 9/13/2023 Not Ready for Inspection WILLIAM MICHALAK
ELECTRICAL-Rough 9/13/2023 Not Ready for Inspection WILLIAM MICHALAK
Green Building Rough 9/13/2023 Not Ready for Inspection WILLIAM MICHALAK
METHANE-Rough 9/13/2023 Not Ready for Inspection WILLIAM MICHALAK
ELECTRICAL-Rough 9/21/2023 Corrections Issued WILLIAM MICHALAK
PLUMBING-Rough 9/21/2023 Corrections Issued WILLIAM MICHALAK
Insulation 9/28/2023 Approved WILLIAM MICHALAK
PLUMBING-Rough 9/28/2023 Corrections Issued WILLIAM MICHALAK
Floor/Roof Diaphrgm/Shear Wall 10/3/2023 Approved WILLIAM MICHALAK
Drywall Nailing 10/11/2023 Approved WILLIAM MICHALAK
Shower Pan 10/27/2023 Approved WILLIAM MICHALAK
BUILDING-Rough-Frame 3/8/2024 Not Ready for Inspection WILLIAM MICHALAK
Final 3/8/2024 Not Ready for Inspection WILLIAM MICHALAK
Green Building Final 3/8/2024 Not Ready for Inspection WILLIAM MICHALAK
Green Building Rough 3/8/2024 Approved WILLIAM MICHALAK
METHANE-Final 3/8/2024 Approved WILLIAM MICHALAK
METHANE-Rough 3/8/2024 Approved WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 3/8/2024 SGSOV Not Ready WILLIAM MICHALAK
Smoke Detectors 3/8/2024 Approved WILLIAM MICHALAK
BUILDING-Rough-Frame 3/27/2024 Approved WILLIAM MICHALAK
Final 3/27/2024 Not Ready for Inspection WILLIAM MICHALAK
Green Building Final 3/27/2024 Not Ready for Inspection WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 3/27/2024 SGSOV Not Ready WILLIAM MICHALAK
Final 4/12/2024 Not Ready for Inspection WILLIAM MICHALAK
Green Building Final 4/12/2024 Partial Approval WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 4/12/2024 SGSOV Approved WILLIAM MICHALAK
ELECTRICAL-Final 4/1/2025 Not Ready for Inspection WILLIAM MICHALAK
Final 4/1/2025 OK to Issue CofO WILLIAM MICHALAK
Gas Test 4/1/2025 Approved WILLIAM MICHALAK
Green Building Final 4/1/2025 Approved WILLIAM MICHALAK
HVAC-Final 4/1/2025 Approved WILLIAM MICHALAK
PLUMBING-Final 4/1/2025 Approved WILLIAM MICHALAK
ELECTRICAL-Final 4/8/2025 Approved WILLIAM MICHALAK
Final 4/8/2025 OK to Issue CofO WILLIAM MICHALAK
Service/Power Release 4/8/2025 Approved WILLIAM MICHALAK