1107 E 102ND ST 90002

Certificate Information: 1107 E 102ND ST 90002

Application / Permit
22016-10000-32457
Plan Check / Job No.
B22LA21536
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of existing attached 2-car garage into new ADU, and laundry room for SFD per CA Govt. Code 65852.2(e)(1)(A).
Permit Issued
Issued on 8/29/2023
Issuing Office
Metro
Current Status
CofO Issued on 6/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/25/2022 APPLICANT
Assigned to Plan Check Engineer 11/1/2022 DANIEL SMILEY
Corrections Issued 11/1/2022 DANIEL SMILEY
Building Plans Picked Up 11/18/2022 APPLICANT
Applicant returned to address corrections 6/27/2023 MINA HABILI
Plan Check Approved 8/24/2023 WEIJIAN HUANG
Issued 8/29/2023 APPLICANT
CofO in Progress 3/12/2024 BEN MOLSTAD
CofO in Progress 3/12/2024 BEN MOLSTAD
CofO in Progress 6/21/2025 DAVID FEILER
Permit Finaled 6/23/2025 RICHARD STEINBACH
CofO Issued 6/23/2025 RICHARD STEINBACH
Permit Finaled 6/23/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/20/2023 NEIL TUANO
Sewer availability Cleared 6/26/2023 NEIL TUANO
Address approval Cleared 6/27/2023 NEIL TUANO

Contact Information

Contractor Owner-Builder       ,
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/29/2023 Partial Approval JOHN KLARIN
Deputy Drilled-In Anchors 10/2/2023 Approved JOHN KLARIN
Footing/Foundation/Slab 10/4/2023 Approved JOHN KLARIN
ELECTRICAL-Rough 11/7/2023 Approved JOHN KLARIN
PLUMBING-Rough 11/7/2023 Approved JOHN KLARIN
Wood Frame 11/7/2023 Approved JOHN KLARIN
Insulation 11/15/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 11/22/2023 Approved JOHN KLARIN
Drywall Nailing 12/5/2023 Approved JOHN KLARIN
Shower Pan 1/3/2024 Approved JOHN KLARIN
BUILDING-Rough-Frame 2/21/2024 Approved BEN MOLSTAD
ELECTRICAL-Final 2/21/2024 Corrections Issued BEN MOLSTAD
Final 2/21/2024 Corrections Issued BEN MOLSTAD
Green Building Final 2/21/2024 Not Ready for Inspection BEN MOLSTAD
Green Building Rough 2/21/2024 Approved BEN MOLSTAD
HVAC-Rough 2/21/2024 Corrections Issued BEN MOLSTAD
PLUMBING-Final 2/21/2024 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 2/21/2024 SGSOV Not Ready BEN MOLSTAD
Smoke Detectors 2/21/2024 Approved BEN MOLSTAD
Final 2/29/2024 Not Ready for Inspection BEN MOLSTAD
Green Building Final 2/29/2024 Not Ready for Inspection BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 2/29/2024 SGSOV Not Ready BEN MOLSTAD
Final 3/6/2024 Corrections Issued BEN MOLSTAD
Green Building Final 3/6/2024 Approved BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 3/6/2024 SGSOV Approved BEN MOLSTAD
ELECTRICAL-Final 3/11/2024 Approved BEN MOLSTAD
Final 3/11/2024 Conditional Approval BEN MOLSTAD
HVAC-Final 3/11/2024 Approved BEN MOLSTAD
PLUMBING-Final 3/11/2024 Approved BEN MOLSTAD
Special/Order Compliance 3/12/2024 Corrections Issued BEN MOLSTAD
Final 10/22/2024 Not Ready for Inspection ANTHONY EGSON
Final 6/21/2025 OK to Issue CofO DAVID FEILER