5678 E HUB ST 90042

Certificate Information: 5678 E HUB ST 90042

Application / Permit
22016-10000-32359
Plan Check / Job No.
B22LA20991
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN **** CONVERSION OF EXISTING GARAGE AND STORAGE SPACE TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 7/18/2023
Issuing Office
Current Status
CofO Issued on 9/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2022 APPLICANT
Assigned to Plan Check Engineer 10/20/2022 SINA KHOSRAVI
Corrections Issued 10/25/2022 SINA KHOSRAVI
Quality Review Completed 10/26/2022 GARO TELMI
Applicant returned to address corrections 2/13/2023 SINA KHOSRAVI
Applicant returned to address corrections 2/15/2023 SINA KHOSRAVI
Applicant returned to address corrections 4/12/2023 SINA KHOSRAVI
Applicant returned to address corrections 5/5/2023 SINA KHOSRAVI
Plan Check Approved 5/25/2023 SINA KHOSRAVI
Issued 7/18/2023 APPLICANT
CofO in Progress 9/13/2024 ALIZAH MAYAGOITIA
CofO Issued 9/17/2024 DEROLD HAUFF
Permit Finaled 9/17/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/2/2022 AMAAN MALIK
Sewer availability Cleared 11/2/2022 AMAAN MALIK
Hydrant and Access approval Cleared 12/13/2022 GILBERT URREA
Construction near power lines Cleared 2/13/2023 RIDWAN HARDY
HPOZ Cleared 4/5/2023 MICAELA TORRES-GIL
Eng Process Fee Ord 176,300 Cleared 4/18/2023 CELINA MORENO
Grading Pre-Inspection Cleared 4/26/2023 ALEXANDER HELFER
GPI Written Notices Cleared 7/6/2023 SINA KHOSRAVI

Contact Information

Architect Worth,, Ann C; Lic. No.: NA37948       ,
Contractor Dco Construction; Lic. No.: 1078972-B       ,
Contractor Dco Real Estate Inc; Lic. No.: 1078972-B       ,
Engineer Ibarra,, Marco A; Lic. No.: C74010 16 N MARENGON AVE STE 604      PASADENA, CA 91101

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 9/6/2023 Corrections Issued DONALD CRICHLOW
Underground Mechanical 10/5/2023 Approved ROY SPAULDING
PLUMBING-Rough 3/4/2024 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 3/20/2024 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 4/18/2024 Approved CRAIG VAUGHAN
HVAC-Rough 4/18/2024 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 4/18/2024 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 4/22/2024 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 5/8/2024 Partial Approval ALIZAH MAYAGOITIA
Green Building Rough 5/8/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Rough 5/8/2024 Approved ALIZAH MAYAGOITIA
Deputy Wood Construction 5/15/2024 Conditional Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 5/16/2024 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 5/16/2024 Approved ALIZAH MAYAGOITIA
Green Building Rough 5/16/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 5/16/2024 Partial Approval ALIZAH MAYAGOITIA
Drywall Nailing 5/22/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 6/6/2024 Approved CRAIG VAUGHAN
Shower Pan 6/6/2024 Approved CRAIG VAUGHAN
ELECTRICAL-Final 7/2/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 7/17/2024 Not Ready for Inspection ROBERT CORNELL
Final 8/23/2024 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 8/23/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 8/23/2024 SGSOV Not Required ALIZAH MAYAGOITIA
Smoke Detectors 8/23/2024 Approved ALIZAH MAYAGOITIA
Final 9/12/2024 OK to Issue CofO ALIZAH MAYAGOITIA
Green Building Final 9/12/2024 Approved ALIZAH MAYAGOITIA