2914 S GENESEE AVE 90016

Certificate Information: 2914 S GENESEE AVE 90016

Application / Permit
22016-10000-32304
Plan Check / Job No.
B22LA21447
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ADU PER STATE LAW IN THE REAR OF THE LOT.
Permit Issued
Issued on 1/5/2023
Issuing Office
Metro
Current Status
CofO Issued on 7/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/24/2022 APPLICANT
Assigned to Plan Check Engineer 10/26/2022 WEIJIAN HUANG
Corrections Issued 10/31/2022 WEIJIAN HUANG
Building Plans Picked Up 11/1/2022 APPLICANT
Applicant returned to address corrections 12/7/2022 DANIEL SMILEY
Applicant returned to address corrections 1/4/2023 VICTOR CHEN
Plan Check Approved 1/5/2023 CRISTINA SALAZAR
Issued 1/5/2023 APPLICANT
CofO in Progress 7/19/2023 JOSE AVILA
CofO Issued 7/24/2023 DEROLD HAUFF
Permit Finaled 7/24/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/7/2022 CHRISTOPHER ROCHA
Roof/Waste drainage to street Cleared 12/7/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 12/7/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 12/8/2022 CHRISTOPHER ROCHA
Flood clearance Cleared 12/30/2022 BRYAN GATHUKA

Contact Information

Contractor Owner-Builder       ,
Engineer Alam,, Anwar; Lic. No.: S5719 372 FLORAL VIEW      IRVINE, CA 92618

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/12/2023 Approved JOSE AVILA
FLOOD-Proofing Certificate 2/7/2023 Partial Inspection JOSE AVILA
HVAC-Rough 2/7/2023 Corrections Issued JOSE AVILA
PLUMBING-Rough 2/7/2023 Corrections Issued JOSE AVILA
Sewer 2/7/2023 Approved JOSE AVILA
ELECTRICAL-Rough 3/1/2023 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 3/1/2023 Partial Approval JOSE AVILA
PLUMBING-Rough 3/1/2023 Approved JOSE AVILA
ELECTRICAL-Rough 3/7/2023 Approved JOSE AVILA
HVAC-Rough 3/7/2023 Approved JOSE AVILA
Deputy Wood Construction 3/13/2023 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 3/16/2023 Partial Approval JOSE AVILA
FLOOD-Elevation Certificate 3/16/2023 Approved JOSE AVILA
Green Building Rough 3/23/2023 Approved JOSE AVILA
Insulation 3/23/2023 Approved JOSE AVILA
Interior/Exterior Lathing 3/23/2023 Approved JOSE AVILA
Drywall Nailing 3/29/2023 Approved JOHN KIDWELL
BUILDING-Rough-Frame 6/1/2023 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 6/1/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
FLOOD-Proofing Certificate 6/1/2023 Approved ALIZAH MAYAGOITIA
Final 6/1/2023 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 6/1/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Final 6/1/2023 Conditional Approval ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 6/1/2023 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 6/1/2023 Approved ALIZAH MAYAGOITIA
Final 6/12/2023 Corrections Issued JOSE AVILA
Green Building Final 6/12/2023 Approved JOSE AVILA
Final 7/17/2023 OK to Issue CofO JOSE AVILA