2914 S GENESEE AVE 90016
Certificate Information: 2914 S GENESEE AVE 90016
- Application / Permit
- 22016-10000-32304
- Plan Check / Job No.
- B22LA21447
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ADU PER STATE LAW IN THE REAR OF THE LOT.
- Permit Issued
- Issued on 1/5/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/26/2022 | WEIJIAN HUANG |
| Corrections Issued | 10/31/2022 | WEIJIAN HUANG |
| Building Plans Picked Up | 11/1/2022 | APPLICANT |
| Applicant returned to address corrections | 12/7/2022 | DANIEL SMILEY |
| Applicant returned to address corrections | 1/4/2023 | VICTOR CHEN |
| Plan Check Approved | 1/5/2023 | CRISTINA SALAZAR |
| Issued | 1/5/2023 | APPLICANT |
| CofO in Progress | 7/19/2023 | JOSE AVILA |
| CofO Issued | 7/24/2023 | DEROLD HAUFF |
| Permit Finaled | 7/24/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/7/2022 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 12/7/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 12/7/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2022 | CHRISTOPHER ROCHA |
| Flood clearance | Cleared | 12/30/2022 | BRYAN GATHUKA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Alam,, Anwar; Lic. No.: S5719 | 372 FLORAL VIEW IRVINE, CA 92618 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/12/2023 | Approved | JOSE AVILA |
| FLOOD-Proofing Certificate | 2/7/2023 | Partial Inspection | JOSE AVILA |
| HVAC-Rough | 2/7/2023 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 2/7/2023 | Corrections Issued | JOSE AVILA |
| Sewer | 2/7/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 3/1/2023 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2023 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 3/1/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 3/7/2023 | Approved | JOSE AVILA |
| HVAC-Rough | 3/7/2023 | Approved | JOSE AVILA |
| Deputy Wood Construction | 3/13/2023 | Conditional Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 3/16/2023 | Partial Approval | JOSE AVILA |
| FLOOD-Elevation Certificate | 3/16/2023 | Approved | JOSE AVILA |
| Green Building Rough | 3/23/2023 | Approved | JOSE AVILA |
| Insulation | 3/23/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 3/23/2023 | Approved | JOSE AVILA |
| Drywall Nailing | 3/29/2023 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 6/1/2023 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 6/1/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| FLOOD-Proofing Certificate | 6/1/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 6/1/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 6/1/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 6/1/2023 | Conditional Approval | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 6/1/2023 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 6/1/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 6/12/2023 | Corrections Issued | JOSE AVILA |
| Green Building Final | 6/12/2023 | Approved | JOSE AVILA |
| Final | 7/17/2023 | OK to Issue CofO | JOSE AVILA |