3344 W HOLLYDALE DR 90039
Certificate Information: 3344 W HOLLYDALE DR 90039
- Application / Permit
- 22016-10000-32210
- Plan Check / Job No.
- B22LA21382
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) 22' X 9-11" DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). AND REPAIR WATER DAMAGED FRAMING. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 12/5/2022
- Issuing Office
- Current Status
- CofO Issued on 9/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2022 | OMAR GARNICA |
| Corrections Issued | 11/1/2022 | OMAR GARNICA |
| Applicant returned to address corrections | 11/23/2022 | OMAR GARNICA |
| Plan Check Approved | 12/3/2022 | MOHAMMAD ESMAILI |
| Issued | 12/5/2022 | APPLICANT |
| CofO in Progress | 9/1/2023 | HAMIK HARTOUNIAN |
| CofO Issued | 9/5/2023 | RONALD MYRICK |
| Permit Finaled | 9/5/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 11/15/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 11/15/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 11/29/2022 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/10/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 2/10/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 2/10/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 2/21/2023 | Approved | HAMIK HARTOUNIAN |
| Sewer | 2/21/2023 | Approved | HAMIK HARTOUNIAN |
| Underground Mechanical | 2/21/2023 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 4/4/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 4/4/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 4/4/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Wood Frame | 4/4/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 4/7/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2023 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 4/7/2023 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/12/2023 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 4/12/2023 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 4/12/2023 | Partial Approval | SCOTT FINNILA |
| HVAC-Rough | 4/12/2023 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 4/12/2023 | Approved | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2023 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 4/17/2023 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2023 | Corrections Issued | SCOTT FINNILA |
| BUILDING-Rough-Frame | 4/24/2023 | Approved | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Green Building Rough | 4/24/2023 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 4/24/2023 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 5/1/2023 | Conditional Approval | SCOTT FINNILA |
| Drywall Nailing | 5/5/2023 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 5/5/2023 | Conditional Approval | SCOTT FINNILA |
| Interior/Exterior Lathing | 6/9/2023 | No Access for Inspection | HAMIK HARTOUNIAN |
| Shower Pan | 6/15/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Final | 8/11/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 8/11/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 8/11/2023 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 8/11/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 8/23/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 8/23/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 9/1/2023 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 9/1/2023 | Approved | HAMIK HARTOUNIAN |