24 E HURRICANE ST 90292

Certificate Information: 24 E HURRICANE ST 90292

Application / Permit
22016-10000-32209
Plan Check / Job No.
B22LA21381
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN REMODEL AND ADDITION TO (E) SINGLE FAMILY DWELLING CONSIST OF: 1- NEW POWDER ROOM IN EXISTING LAUNDRY AREA AT 1ST FLOOR. 2- ENCLOSURE OF EXISTING UNCOVERED DECK TO NEW BEDROOM AT 2ND FLOOR. (165 sqft) 3- RENOVATION AT 2ND FLOOR ACCESS TO BEDROOM
Permit Issued
Issued on 9/3/2024
Issuing Office
Current Status
CofO Issued on 6/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/24/2022 APPLICANT
Assigned to Plan Check Engineer 11/9/2022 JAD BASMA
Corrections Issued 11/13/2022 JAD BASMA
Quality Review Completed 11/23/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 8/16/2024 JAD BASMA
Plan Check Approved 8/27/2024 JAD BASMA
Issued 9/3/2024 APPLICANT
Permit Finaled 6/11/2025 RICHARD STEINBACH
CofO Issued 6/11/2025 RICHARD STEINBACH
Permit Finaled 6/11/2025 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 12/7/2022 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 1/4/2023 DINAH GARIN
Sewer availability Cleared 1/4/2023 DINAH GARIN
Roof/Waste drainage to street Cleared 1/13/2023 DINAH GARIN
Specific Plan Cleared 1/31/2023 VALERIA CEJA
Abandoned oil well Cleared 4/10/2023 KURT CORRAL
Coastal Zone Cleared 8/6/2024 ALEX VELA
Specific Plan Cleared 8/6/2024 ALEX VELA

Contact Information

Contractor Absolute Remodeling Inc; Lic. No.: 914910-B       ,
Engineer Koma,, Shahram Javadi; Lic. No.: NA69497       ,

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/25/2024 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 11/8/2024 Corrections Issued HERBERT GIRON
Deputy Drilled-In Anchors 11/19/2024 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 11/20/2024 Corrections Issued HERBERT GIRON
Insulation 12/3/2024 Partial Approval HERBERT GIRON
Wood Frame 12/3/2024 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 12/12/2024 Corrections Issued HERBERT GIRON
Special/Order Compliance 12/12/2024 Corrections Issued HERBERT GIRON
Deputy Wood Construction 12/13/2024 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 12/16/2024 Partial Approval HERBERT GIRON
Special/Order Compliance 12/16/2024 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 2/4/2025 Corrections Issued HERBERT GIRON
Green Building Rough 2/4/2025 Not Ready for Inspection HERBERT GIRON
Wood Frame 2/4/2025 Not Ready for Inspection HERBERT GIRON
Deputy Wood Construction 2/5/2025 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 2/6/2025 Approved HERBERT GIRON
Footing/Foundation/Slab 2/6/2025 Approved HERBERT GIRON
Wood Frame 2/6/2025 Corrections Issued HERBERT GIRON
Green Building Rough 2/10/2025 Approved HERBERT GIRON
Insulation 2/10/2025 Partial Approval HERBERT GIRON
Interior/Exterior Lathing 2/10/2025 Partial Approval HERBERT GIRON
Wood Frame 2/10/2025 Approved HERBERT GIRON
Insulation 2/13/2025 Approved HERBERT GIRON
Interior/Exterior Lathing 2/13/2025 Approved HERBERT GIRON
Drywall Nailing 2/18/2025 Approved HERBERT GIRON
Final 6/4/2025 Corrections Issued JESUS RODRIGUEZ
Smoke Detectors 6/4/2025 Corrections Issued JESUS RODRIGUEZ
Final 6/9/2025 Partial Approval JESUS RODRIGUEZ
Green Building Final 6/9/2025 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 6/9/2025 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 6/9/2025 Approved JESUS RODRIGUEZ