1682 W WASHINGTON BLVD 90007
Certificate Information: 1682 W WASHINGTON BLVD 90007
- Application / Permit
- 22016-10000-32171
- Plan Check / Job No.
- B22LA21372
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- Fire damage depair to (E) Roof area and Truss. Change portion of warehouse to office
- Permit Issued
- Issued on 5/23/2023
- Issuing Office
- Current Status
- CofO Issued on 12/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2022 | HERNAN ARREOLA |
| Corrections Issued | 11/7/2022 | HERNAN ARREOLA |
| Quality Review Completed | 11/9/2022 | GARO TELMI |
| Applicant returned to address corrections | 12/28/2022 | HERNAN ARREOLA |
| Plan Check Approved | 2/15/2023 | HERNAN ARREOLA |
| Issued | 5/23/2023 | APPLICANT |
| CofO in Progress | 12/18/2023 | ERNESTO CORRAL |
| Permit Finaled | 12/18/2023 | ERNESTO CORRAL |
| CofO Issued | 12/18/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| DAS Clearance | Cleared | 12/20/2022 | Joe Vo |
| Roof/Waste drainage to street | Cleared | 12/30/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 1/3/2023 | TREVOR QUAN |
| Community Plan Implem. Overlay | Cleared | 2/6/2023 | RAFAEL FONTES |
Contact Information
| Architect | Knollmiller,, Jamie Lyn; Lic. No.: NA31366 | , |
| Contractor | Owner-Builder | , |
| Engineer | Allen,, Thomas Christopher; Lic. No.: S5460 | 2 VENTURE, SUITE 200 IRVINE, CA 92618 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/9/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Drilled-In Anchors | 6/27/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2023 | Approved | RAMAZANALI ALMASI |
| Deputy Reinf. Concrete | 8/3/2023 | Conditional Approval | RAMAZANALI ALMASI |
| Deputy Drilled-In Anchors | 8/10/2023 | Conditional Approval | RAMAZANALI ALMASI |
| Excavation/Setback/Form/Re-Bar | 8/14/2023 | Partial Inspection | TIMOTHY POWELL |
| Deputy Reinf. Concrete | 8/15/2023 | Conditional Approval | RAMAZANALI ALMASI |
| Light Gage Steel Frame | 8/24/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2023 | Partial Approval | RAMAZANALI ALMASI |
| Insulation | 8/25/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Interior/Exterior Lathing | 8/29/2023 | Approved | RAMAZANALI ALMASI |
| Light Gage Steel Frame | 9/27/2023 | Approved | RAMAZANALI ALMASI |
| Insulation | 10/4/2023 | Approved | RAMAZANALI ALMASI |
| Drywall Nailing | 10/10/2023 | Partial Approval | JACOB MYERS |
| T-Bar Ceiling | 10/26/2023 | Approved | RICARDO ROBLES |
| Final | 11/22/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 11/22/2023 | Conditional Approval | DARRYL ARNOLD |
| METHANE-Rough | 11/22/2023 | Conditional Approval | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 11/22/2023 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 11/22/2023 | Corrections Issued | DARRYL ARNOLD |
| Wood Frame | 11/22/2023 | Conditional Approval | DARRYL ARNOLD |
| Final | 11/28/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 11/28/2023 | Approved | DARRYL ARNOLD |
| METHANE-Rough | 11/28/2023 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 11/28/2023 | SGSOV Not Required | DARRYL ARNOLD |
| Smoke Detectors | 11/28/2023 | Approved | DARRYL ARNOLD |
| Wood Frame | 11/28/2023 | Approved | DARRYL ARNOLD |
| Final | 12/18/2023 | OK to Issue CofO | ERNESTO CORRAL |