1019 3/4 W 66TH ST 90044
Certificate Information: 1019 3/4 W 66TH ST 90044
- Application / Permit
- 22016-10000-32144
- Plan Check / Job No.
- B22LA21357
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN EXISTING GARAGE TO BE CONVERTED TO ADU (380 SQ. FT.) EXISTING PATIO COVER TO REMAIN ADU CHECKED PER CA GOVE. CODE 65852.2(E)(1)(A)
- Permit Issued
- Issued on 1/24/2024
- Issuing Office
- Current Status
- CofO Issued on 10/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2022 | SUNMIN LEE |
| Corrections Issued | 10/28/2022 | SUNMIN LEE |
| Plan Check Approved | 9/13/2023 | JOSEPH RAFOLS |
| Issued | 1/24/2024 | APPLICANT |
| CofO in Progress | 10/17/2024 | CRAIG DAVIS |
| Permit Finaled | 10/25/2024 | RUBEN SALAS |
| CofO Issued | 10/25/2024 | RUBEN SALAS |
| Permit Finaled | 10/25/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/4/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 11/4/2022 | STEVE MELGAR |
| Construction within easement | Cleared | 2/11/2023 | RIDWAN HARDY |
| Address approval | Cleared | 4/21/2023 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2023 | STEVE MELGAR |
Contact Information
| Contractor | Silva Israel Electric & Plumbing; Lic. No.: 524577-B | , |
| Engineer | Hernandez,, Jose Antonio; Lic. No.: C69472 | 3557 E 58TH ST MAYWOOD, CA 90270 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/2/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 5/2/2024 | Corrections Issued | CRAIG DAVIS |
| Footing/Foundation/Slab | 5/10/2024 | Corrections Issued | CRAIG DAVIS |
| Sewer | 5/10/2024 | Corrections Issued | CRAIG DAVIS |
| Sewer | 5/20/2024 | Partial Approval | CRAIG DAVIS |
| Sewer | 6/20/2024 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Rough | 6/28/2024 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 6/28/2024 | Partial Approval | DAVID FEILER |
| Sewer | 6/28/2024 | Approved | DAVID FEILER |
| ELECTRICAL-Rough | 7/2/2024 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Rough | 7/5/2024 | Partial Approval | CRAIG DAVIS |
| Footing/Foundation/Slab | 7/11/2024 | Approved | CRAIG DAVIS |
| Insulation | 7/11/2024 | Approved | CRAIG DAVIS |
| Wood Frame | 7/11/2024 | Approved | CRAIG DAVIS |
| Insulation | 7/12/2024 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 7/16/2024 | Approved | CRAIG DAVIS |
| Green Building Rough | 7/16/2024 | Approved | CRAIG DAVIS |
| Interior/Exterior Lathing | 7/22/2024 | Approved | JOSH MEISTER |
| Special/Order Compliance | 8/26/2024 | Corrections Issued | CRAIG DAVIS |
| BUILDING-Rough-Frame | 10/3/2024 | Corrections Issued | CRAIG DAVIS |
| Final | 10/3/2024 | Corrections Issued | CRAIG DAVIS |
| Green Building Final | 10/3/2024 | Corrections Issued | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 10/3/2024 | SGSOV No Gas | CRAIG DAVIS |
| Smoke Detectors | 10/3/2024 | Not Ready for Inspection | CRAIG DAVIS |
| BUILDING-Rough-Frame | 10/9/2024 | Order to Comply Issued | JOHN QUINTANILLA |
| Final | 10/9/2024 | Order to Comply Issued | JOHN QUINTANILLA |
| Green Building Final | 10/9/2024 | Order to Comply Issued | JOHN QUINTANILLA |
| Smoke Detectors | 10/9/2024 | Order to Comply Issued | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 10/16/2024 | Approved | CRAIG DAVIS |
| ELECTRICAL-Final | 10/16/2024 | Approved | CRAIG DAVIS |
| Final | 10/16/2024 | OK to Issue CofO | CRAIG DAVIS |
| Green Building Final | 10/16/2024 | Approved | CRAIG DAVIS |
| HVAC-Final | 10/16/2024 | Approved | CRAIG DAVIS |
| PLUMBING-Final | 10/16/2024 | Approved | CRAIG DAVIS |
| Service/Power Release | 10/16/2024 | Approved | CRAIG DAVIS |
| Smoke Detectors | 10/16/2024 | Approved | CRAIG DAVIS |