1019 3/4 W 66TH ST 90044

Certificate Information: 1019 3/4 W 66TH ST 90044

Application / Permit
22016-10000-32144
Plan Check / Job No.
B22LA21357
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN EXISTING GARAGE TO BE CONVERTED TO ADU (380 SQ. FT.) EXISTING PATIO COVER TO REMAIN ADU CHECKED PER CA GOVE. CODE 65852.2(E)(1)(A)
Permit Issued
Issued on 1/24/2024
Issuing Office
Current Status
CofO Issued on 10/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/23/2022 APPLICANT
Assigned to Plan Check Engineer 10/27/2022 SUNMIN LEE
Corrections Issued 10/28/2022 SUNMIN LEE
Plan Check Approved 9/13/2023 JOSEPH RAFOLS
Issued 1/24/2024 APPLICANT
CofO in Progress 10/17/2024 CRAIG DAVIS
Permit Finaled 10/25/2024 RUBEN SALAS
CofO Issued 10/25/2024 RUBEN SALAS
Permit Finaled 10/25/2024 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/4/2022 STEVE MELGAR
Sewer availability Cleared 11/4/2022 STEVE MELGAR
Construction within easement Cleared 2/11/2023 RIDWAN HARDY
Address approval Cleared 4/21/2023 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 4/24/2023 STEVE MELGAR

Contact Information

Contractor Silva Israel Electric & Plumbing; Lic. No.: 524577-B       ,
Engineer Hernandez,, Jose Antonio; Lic. No.: C69472 3557 E 58TH ST      MAYWOOD, CA 90270

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/2/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 5/2/2024 Corrections Issued CRAIG DAVIS
Footing/Foundation/Slab 5/10/2024 Corrections Issued CRAIG DAVIS
Sewer 5/10/2024 Corrections Issued CRAIG DAVIS
Sewer 5/20/2024 Partial Approval CRAIG DAVIS
Sewer 6/20/2024 Corrections Issued CRAIG DAVIS
ELECTRICAL-Rough 6/28/2024 Corrections Issued DAVID FEILER
PLUMBING-Rough 6/28/2024 Partial Approval DAVID FEILER
Sewer 6/28/2024 Approved DAVID FEILER
ELECTRICAL-Rough 7/2/2024 Corrections Issued CRAIG DAVIS
ELECTRICAL-Rough 7/5/2024 Partial Approval CRAIG DAVIS
Footing/Foundation/Slab 7/11/2024 Approved CRAIG DAVIS
Insulation 7/11/2024 Approved CRAIG DAVIS
Wood Frame 7/11/2024 Approved CRAIG DAVIS
Insulation 7/12/2024 Approved BRENDAN MORELLI
Drywall Nailing 7/16/2024 Approved CRAIG DAVIS
Green Building Rough 7/16/2024 Approved CRAIG DAVIS
Interior/Exterior Lathing 7/22/2024 Approved JOSH MEISTER
Special/Order Compliance 8/26/2024 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 10/3/2024 Corrections Issued CRAIG DAVIS
Final 10/3/2024 Corrections Issued CRAIG DAVIS
Green Building Final 10/3/2024 Corrections Issued CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 10/3/2024 SGSOV No Gas CRAIG DAVIS
Smoke Detectors 10/3/2024 Not Ready for Inspection CRAIG DAVIS
BUILDING-Rough-Frame 10/9/2024 Order to Comply Issued JOHN QUINTANILLA
Final 10/9/2024 Order to Comply Issued JOHN QUINTANILLA
Green Building Final 10/9/2024 Order to Comply Issued JOHN QUINTANILLA
Smoke Detectors 10/9/2024 Order to Comply Issued JOHN QUINTANILLA
BUILDING-Rough-Frame 10/16/2024 Approved CRAIG DAVIS
ELECTRICAL-Final 10/16/2024 Approved CRAIG DAVIS
Final 10/16/2024 OK to Issue CofO CRAIG DAVIS
Green Building Final 10/16/2024 Approved CRAIG DAVIS
HVAC-Final 10/16/2024 Approved CRAIG DAVIS
PLUMBING-Final 10/16/2024 Approved CRAIG DAVIS
Service/Power Release 10/16/2024 Approved CRAIG DAVIS
Smoke Detectors 10/16/2024 Approved CRAIG DAVIS