2032 S SHENANDOAH ST unit 8 90034
Certificate Information: 2032 S SHENANDOAH ST unit 8 90034
- Application / Permit
- 22016-10000-31978
- Plan Check / Job No.
- B22LA21243
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ADDITION AND CONVERTING (E) 4-ATTACHED GARAGES TO ONE ADU IN EXISTING APARTMENT BUILDING- PER SATE LAW
- Permit Issued
- Issued on 3/12/2024
- Issuing Office
- Current Status
- CofO Issued on 3/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/26/2022 | SHANGQIN XIE |
| Corrections Issued | 10/27/2022 | SHANGQIN XIE |
| Plan Check Approved | 11/23/2022 | SHANGQIN XIE |
| Issued | 3/12/2024 | APPLICANT |
| CofO in Progress | 1/2/2025 | FARHAD DADBIN |
| Permit Finaled | 3/4/2025 | DAVID TSAU |
| CofO Issued | 3/4/2025 | DAVID TSAU |
| Permit Finaled | 3/4/2025 | DAVID TSAU |
Permit Application Clearance Information
| Highway dedication | Cleared | 11/10/2022 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 11/10/2022 | AMAAN MALIK |
| Address approval | Cleared | 11/15/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 11/15/2022 | AMAAN MALIK |
Contact Information
| Contractor | Sharp Builders & Son; Lic. No.: 1058253-B | 18320 RINALDI PLACE PORTER RANCH, CA 91356 |
| Engineer | , ; Lic. No.: NA69497 | , |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/14/2024 | Approved | FARHAD DADBIN |
| Deputy Drilled-In Anchors | 3/28/2024 | Conditional Approval | FARHAD DADBIN |
| Footing/Foundation/Slab | 3/29/2024 | Approved | FARHAD DADBIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2024 | Partial Approval | FARHAD DADBIN |
| Insulation | 5/9/2024 | Partial Approval | FARHAD DADBIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Interior/Exterior Lathing | 7/2/2024 | Partial Approval | FARHAD DADBIN |
| Drywall Nailing | 7/8/2024 | Partial Approval | FARHAD DADBIN |
| Green Building Rough | 7/8/2024 | Approved | FARHAD DADBIN |
| Insulation | 7/11/2024 | Approved | FARHAD DADBIN |
| Drywall Nailing | 7/16/2024 | Approved | RICARDO ROBLES |
| Interior/Exterior Lathing | 7/16/2024 | Approved | RICARDO ROBLES |
| Final | 10/24/2024 | OK to Issue CofO | FARHAD DADBIN |
| Green Building Final | 10/24/2024 | Approved | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 10/24/2024 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 10/24/2024 | Approved | FARHAD DADBIN |
| Wood Frame | 10/24/2024 | Approved | FARHAD DADBIN |