461 S SAVANNAH ST Unit 6 90033
Certificate Information: 461 S SAVANNAH ST Unit 6 90033
- Application / Permit
- 22016-10000-31949
- Plan Check / Job No.
- B22LA21202
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT (E) REC ROOM TO ACCESSORY DWELLING UNIT (640 SQ FT) PER GCS 65852.2(e)(1)(C)
- Permit Issued
- Issued on 8/1/2023
- Issuing Office
- Current Status
- CofO Issued on 6/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/25/2022 | JOE VO |
| Corrections Issued | 10/26/2022 | JOE VO |
| Plan Check Approved | 1/28/2023 | JEROME MAGAT PALMA |
| Issued | 8/1/2023 | APPLICANT |
| CofO in Progress | 6/3/2024 | RONALD JIMENEZ |
| CofO Issued | 6/5/2024 | ERNESTO CORRAL |
| Permit Finaled | 6/5/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Sewer availability | Cleared | 11/4/2022 | STEVE MELGAR |
| Address approval | Cleared | 11/8/2022 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 11/10/2022 | RUEL COLE |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2022 | STEVE MELGAR |
| Tenant Habitability Plan | Cleared | 1/26/2023 | RICARDO BOHORQUEZ |
Contact Information
| Architect | Nichols,, Mark; Lic. No.: NA38099 | , |
| Contractor | Hernandez Oscar; Lic. No.: 1038687-B | , |
| Contractor | Oscar Hernandez; Lic. No.: 1038687-B | , |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 10/6/2023 | Approved | RAFAEL ESPINOZA |
| METHANE-Rough | 10/6/2023 | Approved | RAFAEL ESPINOZA |
| Wood Frame | 10/6/2023 | Approved | RAFAEL ESPINOZA |
| Drywall Nailing | 10/13/2023 | Partial Approval | KATY RAMIREZ |
| Interior/Exterior Lathing | 11/13/2023 | Approved | RAFAEL CORTES |
| Final | 5/23/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 5/23/2024 | SGSOV Not Ready | RAMAZANALI ALMASI |
| Smoke Detectors | 5/23/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 5/31/2024 | OK to Issue CofO | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 5/31/2024 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 5/31/2024 | Approved | RONALD JIMENEZ |