1218 S NORTON AVE 90019

Certificate Information: 1218 S NORTON AVE 90019

Application / Permit
22016-10000-31948
Plan Check / Job No.
B22LA21201
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(11) Boarding House
Work Description
REPLACE DRYWALL AND PAINTING AT 2-GUESTROOMS
Permit Issued
Issued on 6/26/2023
Issuing Office
Metro
Current Status
Permit Finaled on 10/1/2025

Permit Application Status History

Submitted 10/20/2022 APPLICANT
Assigned to Plan Check Engineer 11/9/2022 ARSALAN SHABESTARI
Corrections Issued 12/12/2022 ARSALAN SHABESTARI
Quality Review Completed 1/6/2023 KEN GILL
Building Plans Picked Up 1/17/2023 APPLICANT
Plan Check Approved 6/22/2023 ARSALAN SHABESTARI
Issued 6/26/2023 APPLICANT
Permit Finaled 10/1/2025 JOEY BUCHANAN

Permit Application Clearance Information

CPC Cleared 3/29/2023 AMANDA KAINER
HPOZ Cleared 3/29/2023 AMANDA KAINER
Eng Process Fee Ord 176,300 Cleared 5/17/2023 CINDY QI
Sewer availability Cleared 5/17/2023 CINDY QI
DAS Clearance Cleared 6/8/2023 ARSALAN SHABESTARI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/26/2023 Corrections Issued JEROME BLACKWOOD
Drywall Nailing 6/27/2025 Partial Approval MARTIN TAVITIAN
Insulation 6/27/2025 Approved MARTIN TAVITIAN
Final 10/1/2025 Permit Finaled JOEY BUCHANAN