1261 1/4-3/4 S DEVON AVE 90024
Certificate Information: 1261 1/4-3/4 S DEVON AVE 90024
- Application / Permit
- 22016-10000-31947
- Plan Check / Job No.
- B22LA21200
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT (E) GARAGE TO 1-STORY 2-UNIT ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33(c)-(d), (g)
- Permit Issued
- Issued on 4/21/2023
- Issuing Office
- Current Status
- CofO Issued on 12/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/26/2022 | DANIEL YIP |
| Corrections Issued | 10/27/2022 | DANIEL YIP |
| Plan Check Approved | 3/10/2023 | DANIEL YIP |
| Issued | 4/21/2023 | APPLICANT |
| CofO in Progress | 12/4/2023 | STEPHANIE SWANSON |
| Permit Finaled | 12/6/2023 | DANIEL ORRANTE |
| CofO Issued | 12/6/2023 | DANIEL ORRANTE |
| Permit Finaled | 12/6/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/27/2022 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 10/27/2022 | HISASHI KOBAYAKAWA |
| Work Adjacent to Public Way | Cleared | 10/27/2022 | HISASHI KOBAYAKAWA |
| "Q" conditions | Cleared | 10/28/2022 | JAZMIN ROQUE |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2022 | HISASHI KOBAYAKAWA |
| Construction near power lines | Cleared | 1/12/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 1/12/2023 | RIDWAN HARDY |
| Specific Plan | Cleared | 1/31/2023 | KEVIN FULTON |
| Specific Plan | Cleared | 2/8/2023 | EDUARDO HERMOSO |
| Grading Pre-Inspection | Cleared | 3/10/2023 | DANIEL YIP |
Contact Information
| Architect | Feld,, Dovid Yitzchak; Lic. No.: C37588 | 921 S HOLT AVENUE LOS ANGELES, CA 90035 |
| Architect | Feld,, Dovid Yitzchak; Lic. No.: NA37588 | , |
| Contractor | Rent Ready Construction Inc; Lic. No.: 1065376-B | , |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/8/2023 | Conditional Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 6/21/2023 | Partial Approval | STEPHANIE SWANSON |
| Deputy Drilled-In Anchors | 6/26/2023 | Conditional Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 6/27/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 6/29/2023 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 8/11/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 8/11/2023 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 8/11/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 8/11/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2023 | Partial Approval | CHRISTOPHER WILSON |
| METHANE-Rough | 9/5/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Shower Pan | 9/5/2023 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 9/13/2023 | Conditional Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 9/13/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 9/13/2023 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 9/14/2023 | Approved | STEPHANIE SWANSON |
| Insulation | 9/20/2023 | Approved | STEPHANIE SWANSON |
| Deputy Wood Construction | 9/22/2023 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 9/26/2023 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2023 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 10/11/2023 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 10/11/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 11/30/2023 | Approved | STEPHANIE SWANSON |
| Final | 11/30/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Final | 11/30/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 11/30/2023 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 11/30/2023 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 11/30/2023 | Approved | STEPHANIE SWANSON |
| Final | 12/4/2023 | OK to Issue CofO | STEPHANIE SWANSON |