7401 S 5TH AVE 90043

Certificate Information: 7401 S 5TH AVE 90043

Application / Permit
22016-10000-31926
Plan Check / Job No.
B22LA21174
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) REC. ROOM TO DETACHED ADU PER ORDINANCE (499 SF)
Permit Issued
Issued on 2/28/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 11/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/20/2022 APPLICANT
Assigned to Plan Check Engineer 10/27/2022 CARLOS MONTES
Corrections Issued 10/31/2022 CARLOS MONTES
Quality Review Completed 11/16/2022 KEN GILL
Building Plans Picked Up 11/28/2022 APPLICANT
Applicant returned to address corrections 2/24/2023 CARLOS MONTES
Plan Check Approved 2/24/2023 CARLOS MONTES
Issued 2/28/2023 APPLICANT
CofO in Progress 11/3/2023 ENRIQUE MIRELES
Permit Finaled 11/26/2023 DEROLD HAUFF
CofO Issued 11/26/2023 DEROLD HAUFF
Permit Finaled 11/26/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/12/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 12/12/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 12/16/2022 CHRISTOPHER ROCHA

Contact Information

Contractor Owner-Builder       ,
Engineer Truong,, Phong; Lic. No.: C70784 20439 E CRESTLINE DRIVE      WALNUT, CA 91789

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/23/2023 Approved ENRIQUE MIRELES
Underground Mechanical 4/5/2023 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 4/11/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 6/1/2023 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 6/1/2023 Approved ENRIQUE MIRELES
Insulation 6/13/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 6/13/2023 Approved ENRIQUE MIRELES
Shower Pan 6/13/2023 Approved ENRIQUE MIRELES
Drywall Nailing 6/21/2023 Approved ENRIQUE MIRELES
Final 9/11/2023 Corrections Issued ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 9/11/2023 SGSOV Not Ready ENRIQUE MIRELES
Smoke Detectors 9/11/2023 Not Ready for Inspection ENRIQUE MIRELES
Final 9/26/2023 Corrections Issued ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 10/10/2023 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 10/10/2023 Approved ENRIQUE MIRELES
Smoke Detectors 10/10/2023 Approved ENRIQUE MIRELES
Final 10/19/2023 Corrections Issued ENRIQUE MIRELES
Final 10/26/2023 Corrections Issued ENRIQUE MIRELES
Service/Power Release 10/26/2023 Approved ENRIQUE MIRELES
Service/Power Release 10/30/2023 Approved ENRIQUE MIRELES
Final 11/2/2023 Conditional Approval ENRIQUE MIRELES