7401 S 5TH AVE 90043
Certificate Information: 7401 S 5TH AVE 90043
- Application / Permit
- 22016-10000-31926
- Plan Check / Job No.
- B22LA21174
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) REC. ROOM TO DETACHED ADU PER ORDINANCE (499 SF)
- Permit Issued
- Issued on 2/28/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 11/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2022 | CARLOS MONTES |
| Corrections Issued | 10/31/2022 | CARLOS MONTES |
| Quality Review Completed | 11/16/2022 | KEN GILL |
| Building Plans Picked Up | 11/28/2022 | APPLICANT |
| Applicant returned to address corrections | 2/24/2023 | CARLOS MONTES |
| Plan Check Approved | 2/24/2023 | CARLOS MONTES |
| Issued | 2/28/2023 | APPLICANT |
| CofO in Progress | 11/3/2023 | ENRIQUE MIRELES |
| Permit Finaled | 11/26/2023 | DEROLD HAUFF |
| CofO Issued | 11/26/2023 | DEROLD HAUFF |
| Permit Finaled | 11/26/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/12/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 12/12/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 12/16/2022 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/23/2023 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 4/5/2023 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 4/11/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/1/2023 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 6/1/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 6/13/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 6/13/2023 | Approved | ENRIQUE MIRELES |
| Shower Pan | 6/13/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 6/21/2023 | Approved | ENRIQUE MIRELES |
| Final | 9/11/2023 | Corrections Issued | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 9/11/2023 | SGSOV Not Ready | ENRIQUE MIRELES |
| Smoke Detectors | 9/11/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 9/26/2023 | Corrections Issued | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 10/10/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 10/10/2023 | Approved | ENRIQUE MIRELES |
| Smoke Detectors | 10/10/2023 | Approved | ENRIQUE MIRELES |
| Final | 10/19/2023 | Corrections Issued | ENRIQUE MIRELES |
| Final | 10/26/2023 | Corrections Issued | ENRIQUE MIRELES |
| Service/Power Release | 10/26/2023 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 10/30/2023 | Approved | ENRIQUE MIRELES |
| Final | 11/2/2023 | Conditional Approval | ENRIQUE MIRELES |