9276-9276 1/2 W FLICKER PL 90069
Certificate Information: 9276-9276 1/2 W FLICKER PL 90069
- Application / Permit
- 22016-10000-31854
- Plan Check / Job No.
- B22LA21106
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN Conversion of existing Basement to ADU in existing 2 story single family dewlling with attached carport per engineer design and details (Attached ADU Contained in Existing SFD per State Law, CA Govt. Code 65852.2(e)(1)(A))
- Permit Issued
- Issued on 8/29/2023
- Issuing Office
- Current Status
- CofO Issued on 3/15/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/25/2022 | AUNG SOE |
| Corrections Issued | 11/9/2022 | AUNG SOE |
| Applicant returned to address corrections | 7/19/2023 | AUNG SOE |
| Plan Check Approved | 7/24/2023 | AUNG SOE |
| Issued | 8/29/2023 | APPLICANT |
| CofO in Progress | 3/5/2026 | DAVID WILLIAMS |
| Permit Finaled | 3/15/2026 | DEROLD HAUFF |
| CofO Issued | 3/15/2026 | DEROLD HAUFF |
| Permit Finaled | 3/15/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 11/9/2022 | MAXFIELD VERMY |
| Address approval | Cleared | 11/10/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/14/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 7/10/2023 | JEANIE LAM |
Contact Information
| Contractor | Dmf Construction; Lic. No.: 1042421-B | , |
| Contractor | Dmfierro; Lic. No.: 1042421-B | , |
| Engineer | Bayat,, Hooman; Lic. No.: C79761 | 16501 VENTURA BLVD STE 400 ENCINO, CA 91436 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Wood Construction | 10/18/2023 | Conditional Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 10/19/2023 | No Access for Inspection | RAUL BARAJAS |
| Wood Frame | 10/19/2023 | No Access for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 10/24/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Rough | 10/24/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 10/24/2023 | Corrections Issued | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 12/27/2023 | No Access for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 12/27/2023 | No Access for Inspection | RAUL BARAJAS |
| HVAC-Rough | 12/27/2023 | No Access for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 12/27/2023 | No Access for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 12/29/2023 | Corrections Issued | RAUL BARAJAS |
| ELECTRICAL-Rough | 12/29/2023 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Rough | 12/29/2023 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 12/29/2023 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 1/23/2024 | No Access for Inspection | STUART CHAPMAN |
| ELECTRICAL-Rough | 1/23/2024 | No Access for Inspection | STUART CHAPMAN |
| HVAC-Rough | 1/23/2024 | No Access for Inspection | STUART CHAPMAN |
| ELECTRICAL-Rough | 1/26/2024 | No Access for Inspection | RAUL BARAJAS |
| HVAC-Rough | 1/26/2024 | No Access for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 2/1/2024 | Corrections Issued | RAUL BARAJAS |
| ELECTRICAL-Rough | 2/1/2024 | Partial Inspection | RAUL BARAJAS |
| HVAC-Rough | 2/1/2024 | Partial Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 2/7/2024 | Conditional Approval | RAUL BARAJAS |
| Drywall Nailing | 3/1/2024 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 3/6/2024 | No Access for Inspection | RAUL BARAJAS |
| Interior/Exterior Lathing | 3/7/2024 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 6/11/2024 | Partial Inspection | RAUL BARAJAS |
| Wood Frame | 6/11/2024 | Corrections Issued | RAUL BARAJAS |
| Interior/Exterior Lathing | 10/29/2024 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 9/10/2025 | Approved | ROY SPAULDING |
| Final | 9/10/2025 | Corrections Issued | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 9/10/2025 | SGSOV Approved | ROY SPAULDING |
| Smoke Detectors | 9/10/2025 | Approved | ROY SPAULDING |
| Final | 1/26/2026 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 3/4/2026 | OK to Issue CofO | DAVID WILLIAMS |