15709-15711 W SIMONDS ST 91344
Certificate Information: 15709-15711 W SIMONDS ST 91344
- Application / Permit
- 22016-10000-31848
- Plan Check / Job No.
- B22LA21099
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVET (E) ATTACHED GARAGE IN TO (N) ADU
- Permit Issued
- Issued on 11/8/2022
- Issuing Office
- Current Status
- CofO Issued on 10/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/19/2022 | FERNANDO FLORES |
| Corrections Issued | 10/19/2022 | FERNANDO FLORES |
| Plan Check Approved | 11/7/2022 | FERNANDO FLORES |
| Issued | 11/8/2022 | APPLICANT |
| CofO in Progress | 9/22/2023 | JENNIFER RABUCHIN |
| CofO Issued | 10/24/2023 | RUBEN SALAS |
| Permit Finaled | 10/24/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/20/2022 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2022 | FERNANDO GIL |
| Sewer availability | Cleared | 10/20/2022 | FERNANDO GIL |
| Grading Pre-Inspection | Cleared | 11/4/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/13/2022 | Approved | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 12/13/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/13/2022 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/28/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| MERV13>=Rough | 12/28/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 1/18/2023 | Partial Approval | WILLIAM WREN |
| ELECTRICAL-Rough | 3/20/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Wood Frame | 3/20/2023 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/26/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/26/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 4/26/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 4/26/2023 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Rough | 4/26/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/26/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 5/3/2023 | Partial Approval | JENNIFER RABUCHIN |
| Drywall Nailing | 5/15/2023 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 6/1/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/7/2023 | Approved | JENNIFER RABUCHIN |
| Pre-Inspection | 6/7/2023 | Approved | JENNIFER RABUCHIN |
| Gas Test | 7/25/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/16/2023 | Approved | JUAN VALENZUELA |
| Final | 8/16/2023 | Corrections Issued | JUAN VALENZUELA |
| Green Building Final | 8/16/2023 | Approved | JUAN VALENZUELA |
| Green Building Rough | 8/16/2023 | Approved | JUAN VALENZUELA |
| MERV13>=Final | 8/16/2023 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 8/16/2023 | SGSOV Not Ready | JUAN VALENZUELA |
| Smoke Detectors | 8/16/2023 | Approved | JUAN VALENZUELA |
| Final | 9/5/2023 | Not Ready for Inspection | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 9/5/2023 | SGSOV Not Ready | RAUL OLAGI |
| ELECTRICAL-Final | 9/18/2023 | Approved | JENNIFER RABUCHIN |
| Final | 9/18/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 9/18/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 9/18/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 9/18/2023 | SGSOV Approved | JENNIFER RABUCHIN |